Onsite – Page 3 – Combined Cycle Journal

WTUI AERO DISCUSSION FORUM: O&M advice free for the asking

By Team-CCJ | April 9, 2024 | 0 Comments

Online forums sponsored by gas-turbine user groups are of increasing value to owner/operators, especially given today’s smaller O&M staffs at simple-cycle, combined-cycle, and cogeneration plants and the loss of experienced personnel to retirement and better opportunities. Long gone are the days of on-the-job training when new employees would tag along with experienced crews to grow their knowledge over time.

Thus, today you may be at a loss on whom to call with an important question. If that’s the case, try posting that question to the forum serving your engine model. Oftentimes you’ll receive expert advice at no cost within a day or two. Most likely your issue is not unique. Also, in need of a part in a hurry? Ask colleagues online to loan you their spare until you can replace it.

Forums serving the larger user groups—such as Western Turbine’s LM6000 Forum—typically provide the best results by virtue of their global reach.

To illustrate the value proposition, CCJ editors selected a few questions posted to the LM6000 forum in 2023 along with a summary of the guidance offered. To join, contact Webmaster Wayne Feragen at wferagen@wtui.com.

  1. Generator vent fans

Question: Has anyone retrofitted their “classic” belt-driven generator vent fan—TCF Azen or Hartzell—to direct drive? If so, whom did you use? Any lessons learned? Where did you source the fans?

Replies:

  • We were a test-bed site for direct-drive fans on both the turbine and generator. Turbine fans were a constant problem and we eventually switched back to belt-driven units. Generator fans—all are TCF/Aerovent—haven’t been as troublesome, but we do suffer intermittent high-temperature issues in summer.
    Whenever we test or inspect, everything checks out OK. We have tried a few minor mods to improve and balance air flow through the enclosure, but haven’t seen a difference. Recommendation: If you are content with your belt-driven fans stick with them.
  • If you’re seeking a retrofit solution to direct drive, I’d recommend contacting Eldridge USA. Their expertise in providing turnkey solutions is noteworthy.
  • Switched to a banded, three-rib V belt and haven’t had anymore belt issues on the generator TCF/Aerovent fans that use a 3/BX73 belt.
  • In the past, apparently there were belt-failure problems on all package fans. We implemented a maintenance program that verifies pulley alignment with a laser alignment tool and setting the proper tension using a belt tension tool. Misalignment and improper tension are the primary drivers of belt failure.

Final step: Use soft starters in the MCC buckets to reduce slippage during starts.

Result: Belt issues essentially have been eliminated at our plant. Today, belts typically are replaced only because of age-related cracking.

  1. Problems with the VBV feedback signal

Question: We have some problems with the feedback signal on one of our variable-bleed-valve systems. It comes and goes, and may be good for several hours/days before it fails again. The OEM’s troubleshooting guide says to measure resistances, check connections, etc. Everything seems fine. Does anyone experience a similar problem? A real solution is important to us, especially in winter.

Replies:

  • Try replacing package and on-engine cables. If the plugs have been overtightened, damage may have been done to the cable sockets.
  • Our site is constantly plagued with VBV and VSV (variable stator vane) feedback problems. Have you looked at any high-speed data logs to see what the signal is doing? Some of our issues have been logic errors that do not prevent nuisance trips when one actuator feedback fails. GE provided new logic (not installed yet) said to resolve several issues with feedback faults causing unwanted action. It doesn’t solve root-cause issues, but it does keep the unit online and rejects the faulty signal.

The responding user provided details on how his plant handles the issue described.

  1. Hole in first-stage HPT blade

Question: During our annual borescope inspection, we discovered a through hole on the leading edge of a first-stage HPT blade. There is a slight amount of TBC loss on the combustor swirlers, but no visible damage or coating loss on the nozzles and later-stage PT blades. We are running five LM6000PCs, but this unit is the only one to have this type of damage. The unit underwent a hot section in 2022 and received a rotable, overhauled HPT rotor at that time with a mixture of new and overhauled first-stage blades. Have any other users had a similar experience or seen this type of damage?

Replies:

  • Several years ago, we had similar damage on our HPT. Cause was identified as liberated material from a combustor secondary swirler (venturi).
  • We’ve had similar failures over the last couple of years. One instance was attributed to an HPC blade event; the second to a nozzle failure, but the exact cause of that was not determined.
  • We experienced similar damage in 2012, with DOD into the HPT first-stage blade. Origin was never determined except that it might have been caused by TBC coating released from the combustion chamber. Blade was replaced in the field.
  1. HCU overhaul intervals, troubleshooting

Question: What do forum participants have to say about the overhaul of their hydraulic control units (HCUs)? Our site has had an HCU fail previously (VBV section). Today we are diagnosing an issue with the VSVs on another unit. Both feedbacks are in agreement, but position became erratic at about 83% stepping up in the positive direction. The issue was bad enough to affect load capability.

Today I performed electrical checks on all LVDTs (just for good measure) and torque motors. All passed. Cranked the unit and stroked the VSVs into several positions, but was unable to replicate. We’re going to check the rod/head screens for any material caught, and possibly replace the HCU.

Replies:

  • Our HCUs failed every time because contaminated oil was fed to the HCU and the internal components clogged-up. Oil contamination was traced to (1) topping off of the GT oil tank with generator oil, (2) the failing HCU filter allowing contaminants to pass through, (3) bypass over the HCU filter, etc. In every event we had to send out the HCU for overhaul. One event was attributed to installation of a short HCU in a long filter bowl.
  • The questioner jumped back into the conversation thusly: Yesterday we ended up replacing the HCU. However, when we loaded the unit at about 48 MW the issue returned. We also received a power-supply fault for the chassis that contains the ACT_CNTRL cards (our PG units have redundant ACT_CNTRL cards, one driving A torque motor coil, the other the B/C coils; both cards are in separate chasses). Today, we will go down the servo cables in the package looking for shorts. If none are found, we will replace the power supply and load the unit again.
  • A concerned user warned: Before you restart the unit, you may want to verify the quality of the synthetic oil to be sure mineral oil was not added inadvertently. Have a SOAP analysis done.
    Continuing, he said, the writer of the first reply shares unfortunate lessons learned. The consequences of continuing to operate with contaminated oil can be significant beyond damage to the HCU. Try to understand why the HCU failed, he recommended. If coking starts to develop in the sumps—especially B&C where the temperatures are highest—the risk of bearing failures is greater.
    He then quoted from the troubleshooting recommendations in Chapter 10 if the O&M manual, “If engine is operated for more than 200 hours with MIL-PRF-23699 oil containing more than 5% mineral oil, significant internal coking may occur.”
  • Another user entered the online chat: One thing to check is the mechanical system to make sure it is free to move across the whole range. The Woodward document had a service-life recommendation for the LM2500+ at six years as I recall. Can’t remember if the LM6000 HCU was in the same document. I will check with the Woodward application team and report back.
    Just rechecked GE documentation and found the service life of the LM6000 HCU is six years or 50k hours.
  • The original questioner reported back: Comments very helpful. We traced the issue to a faulty Woodward actuator control module. It was difficult to trace because we have redundant control of the torque motors (one module connected to torque motor A coil, the other connected to B and C). It seemed from the data log like the issue was common because both cards were stepping up their output. It wasn’t until we ran a calibration on the B channel (B and C coils) that we were lucky enough to catch the erratic behavior from that module at that time. Replacement was the solution.
  • Yet another user closed out the discussion by providing a pdf of Woodward’s HCU manual and an information letter providing recommended maintenance intervals for Woodward auxiliary equipment. The only issues encountered at his plant have been contamination through oil and a grounded servo coil.
  1. VBV actuator/LVDT

Question: We had a VBV actuator feedback fail. Looks like the soldered connections behind the actuator’s Cannon connector were heavily corroded; one of the connections actually broke away at the soldered joint. Is anyone seeing this same failure mode? Might the manufacturer, Arkwin Industries in this case, have had a run of improperly soldered joints?

Replies:

  • The soldering looks to be of poor quality (note that photos of the affected joints were provided via the online forum), but I have seen solder melt inside the package before because of heat if the part is in a hot spot.
    Perhaps the part had been refurbished and misrepresented as new. Suggest you reach out to Arkwin to confirm authenticity.
    Another thought: The O-ring could have been leaking if someone had tried to over-tighten the Cannon plug and twisted it.
  • Questioner response: I agree that the soldering looks nasty. I have only seen Arkwin actuators on our machines, even our old PC model. We are planning to send this one out to AGTSI, having used their service previously for actuator overhaul.
  • Another user, looking at a photo provided by the questioner, confirmed that the actuator is a valid GE Aviation procured part—the Federal Supply Code for Manufacturers is correct as is the part number.
  • Questioner response: This actuator was OEM from GE on our power-generation units. We have never replaced a VBV actuator on these unit until now.
    I did hear back from AGTSI and this is what I was told: Unfortunately, we do not off repairs on these as the manufacturer does not offer this service. That said, however, there are third parties that offer this service but we are not sure if they are approved by the manufacturer. AGTSI does offer rotable exchange for new on these units, but it would be quite a bit more expensive than just having the connections soldered.
  • During the back-and-forth online exchange, Score Energy was identified as a possible service firm for this work.
  • Another user offered the following: From what I understand, Score Energy now is allowed to contract with US end users directly for off-engine parts. The company’s Houston office has competitive offerings on rebuilding, exchange for new, and new outright purchases of LVDTs. However, the rebuild shop is in the UK and there is a long turnover time, so I opted for the new one with the used exchange.
  1. Woodward device needed

Question: Having reliability issues with the auto sync on a unit in our fleet. Don’t have a lot of detail, but the site team believes it’s a malfunctioning DSM. The device is an SPM-D10 Synchronizing Unit (PN 5448-906). According to Woodward, this particular device has not been supported by them since April 2016. Does anyone have any spare devices they are willing to part with?

Replies:

  • A user suggested going on the Woodward website and accessing the company’s list of global business partners to identify service and spare-parts local suppliers that might be able to help.
  • A second user strongly disagreed with the claim suggesting that the auto-sync issue is caused by the SPM synchronizer, as it rarely breaks, he said. The problem often arises when settings on the SPM are not correct, resulting in extended synchronization times unless adjustments are made using the keypad for the SPM.
    I urge you to trouble-shoot the circuitry thoroughly before making any financial commitments. If you pursue the purchase option, you might try Maximum Turbine Support or AP4 Group.
  • A third user found the K100 relay was the issue in a similar situation. The contacts must get gummed-up and do not pass good voltage to the input card, he said. It happened on two different units, so plant replaced the relays on all four of its PD engines, which have MicroNet Plus control systems.
    This was for the remote auto sync and not the local TCP. Our site is set up with a remote supervisory control system that controls all the units and tells them to synchronize remotely (enable sync). If we went out to the site and put the TCP in “local” and then moved the hand/off/auto switch from “off” to “auto” it would synchronize just fine, but wouldn’t sync if told to do so remotely. Not sure if this applies to your situation.
  • As the previous user said, make sure the permissive signal (coming from the K28 relay in my unit) is active during auto sync. If it’s taking a long time to auto sync, check the DSM settings and fine-tune as necessary.
  • Yet another user noted that while the SPM-D10 Synchronizing Unit rarely breaks, he had to replace one recently because of a failed breaker-close output relay.
  • The previous user agreed that the DSM was very robust and surmised that if the breaker-close output relay is damaged there could be a loose connection in the breaker closing circuit.
  1. Likelihood of a major combustor problem

Question: After all the discussion about combustor problems at this year’s WTUI conference and the general unavailability of spare parts for these components, we are evaluating the logic of ordering a spare hot-gas section. We have two PF2 engines and neither GE nor the ASPs have much in the way of spares.

What is the likelihood of a major problem in the hot-gas section of these units? Are any numbers available? Does someone have a spare hot-gas section? What is your strategy?

Replies:

  • Very complex question, so the response is multi-faceted. Capital expenditures—such as purchasing a spare hot section—depend on many factors, including the following:
  • Mode of operation—peak, load-following, baseload.
  • Annual operating hours, which impacts the calendar time between hot sections.
  • Inlet filtration quality.
  • Size of installed fleet.
  • Operating experience.
  • Operator experience, fuel quality, number of trips, etc.
    My company will be operating multiple baseload units in several plants trying to run as close as possible to 8760 hours annually. Considering today’s supply-chain challenges, we will own a spare hot section to rotate through the “fleet,” maximizing the number of available hours to operate.
    If an owner operates relatively few hours in a seasonal pattern (for example, high demand in summer or winter), then it might be able to coordinate with the OEM to have the replacement got section available at the “right time” and not have to buy a spare.
  • Having a spare hot section probably is overkill if you have only two units. However, if the units must have super-high uptime, then you need to weigh the cost of the hot section against the cost to the business when the unit is not operational. Something to consider: What happens if you buy a combustor and put it on the shelf and GE updates the design?
  • I think routinely checking your T-48 spread and adjusting your fuel-nozzle pattern accordingly, along with routine borescope inspections of your dome cup area, inner/outer liners, and looking for early signs of spalling TBC, is a good proactive approach regarding hot-section life.
    I would also look at NOₓ water mapping to be sure you are not over-watering your combustor. Over-watering and harmonics are the biggest causes of cracking around the cooling holes located behind the dome cup area that can cause downstream HPT first- and second-stage damage.
  • How many fired hours will your two PF2 units be operating annually? If 8000 to 8500 hours, the best solution is to purchase a spare engine and rotate it into operation at each hot section and major. The spare engine is conducive to a short outage duration for swapping engines and maximizes unit operating hours. The hot section or major maintenance would be completed on the engine removed after the unit is back in service and before the next unit is due.
    Keep in mind that you don’t want both units scheduling hot sections and majors at the same time—if the units are operating nearly the same annual hours. Reason: You would need hot-section parts for two units at the same time, compounding the issue. It would be best to get one unit into the first hot section (or swap the spare engine in) a year early to offset the hot section and major outage intervals for the two units.
    If the units will be operating less than 4000 hours annually and not so critical for availability, you might not need a spare engine.
  • We are currently evaluating our needs for the new PF1 units we are installing, but more than likely will keep at least one spare engine on hand for our 10 units, with the possibility of upping that to two. We did consider purchasing a spare hot section as well, but the cost of the that section with the combustor included is near enough to the cost of having another complete spare engine that we’re not sure it makes sense for us.
  • Follow-on response from the user asking the original question: Looks like we’re actually investing in a spare engine for several reasons—including minimizing downtime, advantages for major maintenance work, and assuring the district heating supply.
    However, the final decision hinges on what costs we should expect for preservation of the spare engine? Are there any maintenance or conservation activities that must be conducted regularly? Is it possible to estimate the costs involved?
  • This response to the second round of questions: Get familiar with WP 3011 in the O&M manual. Plus, consider storing the gas turbine in its container inside a warehouse, or if has to be outside, place it under roof cover. When the container expands and contracts because of weather changes, and especially if it sits in the sun, the ability to keep the internal humidity under control is much more difficult.

7F Users Group 2023: User Presentations and Discussion

By Team-CCJ | April 2, 2024 | 0 Comments

Seasoned owner/operator personnel tackle the biggest industry issues

 The depth and breadth of experience represented by 11 owner/operator presentations at the 2023 7F Users Group Conference can be summed up like this:

  • Chronologically, they represent machines dating back to the original F-class gas turbines (GT) off of the test stands in 1988.
  • Numerically, these users are responsible for at least 150 7F units, maybe closer to 200.

The presenters themselves are some of the most seasoned experts in GT operations and maintenance in the nation; many are names familiar to the GT user group community. Topically, the presentations can be grouped as follows:

  • Two deep dives into specific compressor issues.
  • Two deep dives into specific combustor issues.
  • One addressing myriad control-system issues.
  • One discussing the exhaust end.
  • One on turbine-bucket creep failure.
  • A primer on the latest 7F combustor system (the DLN 2.6+).
  • One on a fuel-gas stop/speed ratio valve actuator.
  • Two “system” presentations on lifecycle management and R&D aspects.

At the risk of sounding like a late-night Ronco commercial, don’t delay. After reading the high-level summaries presented here, go to www.powerusers.org and look at the slides, available for viewing to user members of Power Users (user non-members will have to apply and be approved by the leadership). If you are responsible for 7Fs in your fleet, the editors believe you’ll be glad you did. Don’t forget to register for the 2024 annual conference this May.

Beware shrouded S17 blades

An owner/operator representative with 15 7F units dating back more than 30 years described the company’s strategy for replacing, upgrading, and enhancing the compressors in the fleet and subsequent operating experience. The program began in 2009 and the last of the simple-cycle units is expected to be completed in 2025.

Others with or eyeing shrouded contoured S17 blades as an enhancement, take note. The presenter’s conclusion is succinct and blunt: The enhancements went smoothly and performed well except for the shrouded S17s. Two units experienced pressure-side root rubs in the S17s, which subsequently had to be “surgically removed and replaced.”

Execution lessons learned include making sure to use the right gages (taper versus feeler) in the right places when collecting all the necessary data, walking down the rotor transport route as each site is different, and managing expectations on the condition of a “just in time” rotor in layup.

Addressing T-fairing distress

Described in TIL-2212, T-fairing is a circumferentially loaded platform on the compressor rotor that has an inner flow path between R1 and R2 and R2 and R3 under the tips of variable stator vanes (VSV) 1 and 2. An expert for an owner/operator with a fleet of over 50 7F machines noted the general concerns: VSV tip rubs and liberated material, circumferential gaps and T-fairing shingling leading to rotor imbalance, compressor blade platform damage, and rotor/wheel dovetail slot wear.

The presenter noted that the three TIL revisions to date, the most recent in August 2022, express a progressive level of urgency to address this issue. Recommendations to mitigate the original T-fairing operational risk include:

  • Borescope inspection (BI) as specified in the TIL to inspect for VSV tip loss, excessive gaps, and wear/rubs.
  • Monitor units even more closely if equivalent turning gear (ETG) hours are greater than 15,000.
  • Monitor T1 and T2 seismic vibrations; alarm at 0.50 in./sec, runback at 0.82 in./sec, and trip at 1.00 in./sec.
  • If T1/T2 alarm is triggered via step change, inspect at next opportunity and suspect T-fairing shingling or hard rub.

When replacing T-fairing, ensure lockers did not migrate or disengage per TIL-2391: Torque-check exposed lockers (four per stage) in R3-R6, and BI R7-R14.

Results with DLN2.6+ with AFS/OBB

An owner/operator with 32 7F machines in its fleet reported on turndown performance after retrofitting four FA.04 units at one site, between 2020 and 2022, with dry low NOₓ (DLN) 2.6+ combustion hardware along with axial fuel staging (AFS) and overboard bleed (OBB).

While all of the machines met or exceeded their performance guarantees (numerous graphs provided), the user did underscore effusion-plate cracking found during a spring 2023 BI after 25,000 fired hours affecting 14 of 56 combustor cans. The OEM plans to modify the area with thermal barrier coating (TBC) per TIL-2292 at the next hot-gas-path inspection (HGPI).

Separately, the speaker noted that limited tuning capability on the part of the OEM’s service team for this new technology led to 12 schedule modifications. Up to 12 days were required to tune each 2 × 1 block.

Other lessons learned: Ensure outside instrumentation is heat-traced (a compressor discharge pressure transmitter for the AFS froze up and kicked out AFS operation); ensure that the SSO (safety shutoff) valve blank is removed (caused a two-day delay getting back online); check for looseness in the AFS damper (one-day delay for inspection and tack welding); and have a backup emissions analyzer available.

Combustor end-cap failure RCA

You’ll have to check out the slides to experience the “perfect storm” which led to a catastrophic failure in 2023 of combustor end caps following a flange-to-flange replacement in 2022 of an unflared 7FA.01 (with 181,000 fired hours) to a flared 7FA.04 with DLN2.6+ and AFS.

Some of the elements in the storm were the result of what the presenter called “downgrades” from the replacement (as opposed to “upgrades”)—such as switching the control system from Ovation to Mark VIe and changing the tuning option from manual to the OEM’s Autotune MX.

As recently as October 2022, a BI turned up no significant findings on the unit. The presenter’s frustrations with the OEM are also clear in the slides, especially when poking fun at the OEM’s euphemisms and obfuscating language. Reportedly, the OEM was essentially no help during the short-term recovery of the unit after this catastrophic failure; site personnel had to figure stuff out on their own. As for a long-term solution, a new TIL to fix the bugs in Autotune, which disregarded the high dynamics (a key part of the “storm”), wouldn’t be available until fall 2023.

Cornucopia of controls issues

One of the industry’s leading user experts on GT controls reviewed myriad issues, some associated with TILs, but also controls associated with emergency bearing-oil pumps and lube-oil seal-pump starter failures; liquid-fuel purge systems; non-optical flame detectors; high turbine-compartment temperatures; compressor-bleed-valve drain lines; modified exhaust-temperature-spread monitoring in EMS2100, Mark VIe TTUR card (associated with the primary trip terminal board) failure associated with generator synchronizing out of phase; and compressor discharge temperatures.

Robust exhaust replacement

These slides offer a pictorial view and chronology of an exhaust-system replacement at a 2 × 1 combined-cycle facility. Drivers for the project included exhaust liner cracks, flex-seal failures, horizontal joint separation, high exhaust-frame-blower amperage readings, and frequent exhaust-frame-blower motor change-outs over the five years before the project. Solution was to replace the back end with the OEM’s “Robust Exhaust Upgrade.”

Post-installation photos are included of both units, one after 1500 hours and 15 starts, and the other after 19,000 hours and 70 starts. Graphs show that the blower motors are operating generally below the threshold of high amperage. One caution: Be sure to thoroughly check that no insulation is missing if you are planning one of these replacement/upgrades.

Fleet R&D activities

A representative from the Electric Power Research Institute (EPRI) identified and expounded upon areas where R&D is being conducted on behalf of all EPRI member fleet owner/operators. Examples offered of R&D projects with “proven value” include the following:

  • Using EPRI’s digital-twin technology for managing regular maintenance activities and enhancing GT dispatch.
  • Balancing operational risks from power augmentation with market opportunities to sell additional megawatts during high-price periods.
  • Providing guidance on overall quality control and assurance during major planned HGP outage activities.
  • Applying additive manufacturing to enhance first-stage vane cooling and overall engine performance.
  • Applying process component resonance (PCR) testing to validate repairability of second-stage turbine blades.
  • Demonstrating 20% to 40% hydrogen blending in LM6000 and 501G units.

Second-stage-bucket creep failure

A metallurgist for one of the largest fleet owners in the US analyzed the March 2022 failure of 7FA.03 second-stage buckets in a combined-cycle unit with commercial online date (COD) of 2007. The failure occurred after a shutdown on abnormal vibration following 22,300 hours and 95 starts since the last HGPI in November 2018. A subsequent BI showed S3B material liberation but no evidence of foreign object damage.

Further inspection revealed SB2 degradation on 92 10-hole (cooling) blades supplied by a third party, including airfoil impact damage/cracking on 14 blades, shroud damage on 89 blades, missing leading-edge shrouds on four blades, and shroud cracking on 85 blades. Regarding the SB3 row, all blades lost shroud area, but there was no noticeable root damage or fractured, heavy impact damage.

Fourteen of the third-party S2B blades were compared to original OEM blades and it turned out that airfoil and tip shroud geometries were not placed in the same position and bucket tips were lifted significantly. Six S3B blades similarly compared were consistent except one blade showed localized differences because of bending from impact damage.

Overall, there was “strong evidence” of creep damage in the S2B shrouds and no noticeable evidence of creep damage in the S3B shrouds. Site-to-site comparisons of operating data revealed that the failed unit runs relatively hotter than the other 7F.03s in the user’s fleet—similar to Dot 04s in fact, based on historical exhaust temperature data. Long-term solution was to replace the S2B rows of blades with ones of OEM design.

Component lifecycle management

While these slides act mostly as prompts for a facilitated discussion with the audience, they do offer insights into what is keeping this owner/operator GT expert up at night. In particular, as components approach end of original expected life, there is competition for supply of new parts and shop refurbishment space.

Meanwhile, additional lifecycle issues continue to be discovered, putting additional pressure on fleet owner/operators. Another complicating factor: OEM TILs and bulletins go through many revisions. The presenter cited GER 3620, now on revision P (2021).

If you and your team are trying to set an overall fleet life and refurbishment strategy, this likely is a presentation worthwhile reviewing.

Fuel-gas SRV actuator issue

At this 7FA.05 site, the safety/speed ratio valve (SRV) (with digital valve positioner DVP) tripped on a fault, then the same SRV tripped in the companion unit. The first unit then tripped twice, after the SRV was repaired, because of relay issues. There was actuator gear damage, for which the OEM is performing an RCA. The P2 cavity pressure transmitter reading was fluctuating rapidly, but once the input filtering was changed, the fluctuations were greatly reduced.

Although the site-specific details (including many control system diagrams, jargon, and acronyms) are available in the slides, the action items are probably of most use to readers:

  • Have full SRV spares available, including the DVP, onsite and back-up the DVP software.
  • Make sure spare relays and contacts are available and test new relays in the shop before stocking them in the warehouse.
  • Be familiar with Woodward diagnostic tools and software.
  • Lubricate actuator and stroke valves periodically.
  • Monitor deviation between valve command and feedback.
  • Review alarming strategy and configure additional signals if necessary.
  • Review P2-cavity pressure-transmitter signal input filters and adjust as necessary.

DLN2.6 system tuning

This user presentation with over 50 slides is essentially a primer on the DLN2.6 combustion system. Broad topics covered include an introduction to fire and flames, fuel gas system and combustion components, control variables and terminology, DLN modes and startup sequence, acoustic dynamics, emissions, DLN2.6 tuning, and overview of DLN2.6+ and AFS.

7F Users Group 2023: Vendor Presentation Recaps

By Team-CCJ | April 2, 2024 | 0 Comments

After reading the high-level summaries of the vendor presentations from the 2023 7FUG presented here, go to www.powerusers.org and look at the slides, available for viewing to user members of Power Users (user non-members will have to apply and be approved by the leadership). If you are responsible for 7Fs in your fleet, the editors believe you’ll be glad you did. Access an overview of the end user presentation and discussion topics here.

Gas turbines

Gen 2 combustor-cap effusion plate design is said to have a service life of 48,000 hours and 1800 starts (Fig 1). It takes advantage of the vendor’s stated unparalleled repair experience with liners, transition pieces, and caps over 18 years. Expansive design details include new materials, new cooling-hole dimensions, more closely spaced outer-diameter holes, changes to lip height, and others. Slides offer a thorough review of OEM and Gen 1 designs and operating history. Presenter challenges the notion that the OEM’s Technical Information Letter (TIL) recommendation to include a thermal barrier coating (TBC) to the part will always solve problems.

Design and Development of a DLN 2.6 Combustor Cap Effusion Plate, Aaron Frost, APG

 

Flow testing of transition pieces, an “uncommon practice” in the industry, has been implemented at vendor’s shop for combustion-system optimization. It can help address exhaust-temperature-spread issues, ease combustor tuning, and assist in troubleshooting. Photos of sonic and vacuum flow testing equipment are included, along with diagrams and descriptions of combustion system components.

Combustion System Optimization, Jim Neurohr, Sulzer Turbo Services Inc

 

Single-crystal components are “fully repairable,” with attendant performance improvements, and has been demonstrated through company’s experience, beginning with an EPRI demonstration project. Case studies review first-stage-blade tip restoration and coating, and first-, second-, and third-stage nozzle repairs.

Gas Turbine Parts Repairs and Solutions, Jose Quinones, MD&A

 

Upgraded 1-2 spacers featuring 11% cyclic stress reduction are just one of several component replacement and repair options as a result of company’s reverse engineering, production, and repair development programs. There are “replacement options for all problematic components,” and repairs to correct disc issues, compressor dovetail cracking, first-stage-disc balance weight and groove cracking, first- and second-stage-disc cooling-slot cracking, 1-2 spacer rim cracking, and second-stage-disc lockwire-slot cracking, among others.

7FA Rotor Life Assessment with 1-2 Spacer Cracking Evaluation, Mark Passino, MD&A

 

Failure analysis can be a “strong learning opportunity,” says the presenter of this tutorial, which is based on a chapter from a one-day course offered by the vendor. Collecting O&M data and history, conducting root-cause analysis, elements of expert witness activities, writing good reports, and metallurgical analysis and NDE techniques are all explored (Fig 2). Conclusion? An expert at failure analysis is a “bad-ass miracle worker.”

GT Failure Analysis, Doug Nagy, Liburdi Turbine Services Inc

 

Exhaust noise at a simple-cycle GT site is addressed in a case study including problem definition, site engineering (noise study, vibration testing, and thermography), modeling, engineering solution, and evaluation of performance, which proved to be better than predicted. The 9 × 9 bar silencer array and modified turning-vane set subsequently installed also reduced total pressure loss by 0.5 in. H₂O.

Dynamic Case Studies on Turbine Exhaust Systems—Gas Path Upgrades, Scott Schreeg, SVI Industrial

 

Managing end-of-life (EOL) rotor issues requires at least a two-year planning cycle, maybe three, if you have one of the 400 7F units installed between 2000 and 2004. Reason: A hundred of those rotors will need major service or replacement over the next few years. Presenter covered many life evaluations, upgrade packages, and replacement options—including complete flared and unflared offerings—as the industry struggles to handle the volume of 7F EOL needs.

Managing the 7F Rotor Wave with Ingenuity, Brian Loucks and Katie Koch, PSM, a Hanwha company

 

Hypothetical nighttime emergency trip at full speed/full load is imagined to illustrate how company can work with a customer after the borescope inspection reveals heavy compressor damage. Simulated failure situation steps through mobilization of field service crew, preservation of evidence, on- and offsite activities, in-shop rotor evaluation, client reports, repairs/coatings, replacement parts and manufacturing, rotor balancing, root cause analysis, materials evaluation of failed components, and rotors and components successfully returned to site and put in service.

A Bump in the Night, Jim Neurohr, Sulzer Turbo Services Inc

 

Options for extending unit turndown to remain relevant during the market transition from fossil fuels to non-carbon energy sources are explained. Options are anchored by the vendor’s Ecomax® software, including the integration of inlet-guide-vane (IGV) angles with an inlet-bleed-heat (IBH) engineering upgrade. Interestingly, investment attitudes, based on a popular annual survey of executives, around solar, wind, and storage dropped significantly between 2021 and 2022, while natural gas grew three percentage points.

Turndown or Shutdown? Combatting the Effects of Increased CCGT Cycling, Jeff Schleis, EthosEnergy Group

 

Fleet issues with exhaust frames are described and enumerated, along with company’s upgrades for the flex-seal retention assembly, L seal monoblock, parting joint, and airfoil and insulation packages. Replace, refurbish, and repair decision methodologies are illustrated with several case studies.

7F Exhaust Frame R3 Modifications and Upgrades: 2023 Update, David Clarida, Integrity Power Solutions

 

Upgraded or repaired liner plates in transition ductwork between the turbine exhaust and HRSG can be provided along with exterior (for example, thermography) online, and interior offline, inspections to identify problems and failure areas. Also discussed are services around compliance with the ASME Power Piping Code for high-energy and covered piping systems. Expansion joints, HRSG pipe penetration seals, and HRSG inspection and performance analysis complement vendor’s portfolio of services.

7F Transition Duct Liner Plate & HRSG High Energy Piping Programs, Ryan Sachetti, IAFD

 

Water-repellent air intake filters made of synthetic materials are now available from company which has been exclusively supplying one major GT vendor since 2019 and now has special agreement for the US market beginning 2023. Data from case study of an F-class unit in a coastal wet/foggy northern European plant supports claims of better performance. Other company capabilities: acoustics, wet compression, evaporative coolers, chillers, and anti-icing systems.

New ISO 29461-2 for Gas Turbine Air Inlet Filters, Gianluca de Arcangelis, NRG-Faist

 

HRSGs

Fouling of HRSG tubes, contributing to higher turbine exhaust backpressure adds risk for machine trips and runback during cold-weather operation, which has been under the regulatory microscope in recent years. Actions for preventing gas-side fouling are presented, with a caution not to ignore baffles, relatively inexpensive and often overlooked. Expert examines six topics which, when addressed together, can restore up to six megawatts of output.

Improving HRSG Efficiency with Operational and Design Modifications, Cesar Moreno, HRST Inc

 

HRSG tube-plugging options are worthy of consideration because “tube leaks happen” and often it is necessary to get the unit back online quickly (Fig 3). Generally, though, you should strive to fix the leak and seek to identify and address the cause. Slides run through the typical causes of tube leaks with plenty of detail on four tube plugging options, attention to ASME Boiler & Pressure Vessel and National Board Inspection Codes; and pros and cons of plugging. Always insist on a documented repair plan before beginning a plugging project and be sure to stock tubes and plug materials.

HRSG Tube Plugging Strategies to Simplify Tube Leak Repairs in Aging F-Class Units, Lester Stanley and Rich Miller, HRST Inc

 

Steam turbines

Warming your steam turbine and HRSG between shutdown and startup addresses fatigue issues, emissions and fuel consumption, and performance losses. A D11 case study reveals impressive results, such as combined-cycle start times improving from 266 to 149 min (Fig 4), and reduction of high-pressure-rotor life consumption by 25%. Photos and explanation of sophisticated insulation and electric warming systems for ST/Gs are provided. A beta site is being sought for a new HRSG warming system developed with EPRI. Vendor has added onsite machining services for steam valves.

Complete Cycle Solution for Optimized CCGT Startup, Pierre Ansmann, Arnold Group

 

Generators

Emergency purge of generator H₂ coolant can avoid catastrophic loss during fires, seal-oil issues, H₂ piping failures, and severe weather events.  A photo montage of explosions reveals how serious such loss can be. Fast-purge package, including the fast degas CO₂ skid and gas monitoring and control piping, allows all purge operations to be managed from the control room via DCS or locally on HMI. System also can reduce purge times to less less than one hour.

Benefits of the Generator Fast-Purge Package on a GE7FH2 Generator, Rob Kallgren, Lectrodryer

 

Generator collector performance depends on consistent and adequate brush film, adequate contact pressure, proper ring surface conditions, and continuous brush-to-ring contact. Daily/weekly monitoring with minor maintenance is key. A plethora of photos document and illustrate common problems and solutions such as footprinting (also called ghosting, photographing), brush restrictions, brush-holder spacing and alignment, contamination, wear patterns and mechanisms, repair indications, collector-ring resurfacing, and vibration.

Generator Collector Performance and Maintenance, Jamie Clark, AGT Services

 

Complete stator replacement is reviewed as a veritable photographic journey for a unit which, in October 2020, experienced core looseness at the turbine end and broken off core laminations (Fig 5). Site involved has two 2 × 1 blocks with dual-fuel 7FA gas turbines, one block with a D11 steamer (commissioned in 2011) and the other with an Alstom turbine/generator (commissioned in 2006).

7FH2 Stator Replacement, Shawn Downey, MD&A

 

General, BOP

Incorrect tightening of bolts can lead to catastrophic failure, and bolt stretch is a key factor in proper bolt tightening, because stretch is directly proportional to the tensioning force applied. A detailed list of tips for proper tightening is included in Fig 6.

Coupling-Stud Stretch Measurement Can Make or Break Turnaround Time, Dan Johnston, Riverhawk

 

Polyalkylene glycol (PAG)-based electrohydraulic control (EHC) fluids are compared to several different phosphate ester formulations, with pros and cons delineated for each. After 10 years of use at one site, vendor’s PAG-based EcoSafe EHC S3 DU showed an impressive total acid number, a key performance index. One powerplant with three steam turbine/generators running on the same charge of this fluid reported “no issues with system pumps, servos, or actuators, no detrimental effects on fluid from temperature excursions, and fewer issues with moisture contamination.”

PAG-based EHC Fluid, a Sustainable Alternative to Phosphate Ester for EHC Application, Chris Knapp, Shell Lubricant Solutions

 

The Mobil™ turbine-oil triage chart can be applied for mitigating varnish, says presenter, after you’ve assessed the situation you are trying to address (extend outage intervals, correct operational issues, support future conversions) and gathered basic information and conducted a root-cause analysis. Impact photos from the use of several different Mobil products and services are included.

Mobil™ Turbine Oil Triage Guide, Chandler Rogers, Mobil

 

Third-generation dual-fuel water-injection system components (Fig 7) are said to have performed very well at the customer site referenced: liquid-fuel starts and transfers exceed the “industry standard success rate,” purge-air check valve operates with no leakage, check valves and three-way purge valve experienced no failures over multiple years, and water-injection flow proportioning valve operated multiple years without failures, despite thousands of hours of downtime.

20 Years of Reliability: A System-Based Case Study, Dual Fuel with Water Injection, Schuyler McElrath, JASC

 

Comprehensive weather readiness assessment can help ensure that your site complies with latest regulatory mandates that plants provide maximum and minimum ambient dry-bulb temperatures to which units can operate without a forced outage, derate, or failure to start. Checklists for turbine/generators; fuel supply, plant air, lube oil, cooling, and water systems; and cabinets and compartments are included.

Extreme Temperature Readiness, Jason Neville, TG Advisors

 

Expanding sleeve bolt technology can avoid problems like seized fitted bolts and studs, which often have to be destroyed to be removed and can lead to damage to the coupling holes themselves, extending downtime. Vendor’s EZFit technology can be considered a permanent replacement for other prevalent designs.

Turbine/Generator Coupling-Bolt Solutions, Peter Miranda, The Nord-Lock Group/Superbolt

 

Tutorial on the use of hydrogen as a fuel includes H₂ properties, sources, value-chain considerations, percentage in blends, industry experience, and challenges to adoption.

H₂ as a Fuel for GTs in the Power Industry, Gus Graham, CRDX Carbon Reduction Systems

 

High-pressure water-mist systems for fire suppression are explained, then compared to other options such as CO₂, Halon, dry chemical, inert gas, and low-pressure water mist. Three HP water-mist delivery-system designs (skids, fluid containers, piping) are illustrated. Meeting water quality recommendations is a must when using these systems, and design should meet the NFPA definition of water mist—99% of droplets at minimum operating pressure are less than 1 mm in diameter (layman’s version).

Water Mist Fire Suppression for Power Generation, Dale Shirley, Marioff NA

 

Controls

Findings and observations from the perspective of an owner’s engineer during the upgrade of two gas turbines from a Mark VI/EX2100/LS2100 to a Mark VIe/EX2100e/LS2100e control system are presented.

Control Solutions, Abel Rochwarger, GTC Control Solutions, a division of AP4 Group

 

The impact of instrument-related events on machine reliability opens this slide set, with statistics worth contemplating—for example, upgrades and maintenance would have prevented 40% of the reported failure events. Balance of preso reviews reliability assessments for exciters and load commutated inverters (LCI), component replacement intervals, maintenance and testing of on-shelf electronics, TILs associated with these components, and performance evaluation.

Exciter and LCI Controls Reliability for 7FA Gas Turbines, John Downing, TC&E, a division of AP4 Group

 

Reactive, proactive, and predictive M&D services have been developed around the company’s digital products, primarily Autotune, now serving over 100 assets. Examples of the three types of M&D are included. Under proactive, for example, are checking combustor dynamics signals during transients and early signs of combustion anomalies. Predictive examples are based on comparing unit performance to a larger fleet of machines.

Digital-Twin Alignment Between Design Intent and Real-World Power Plant Operation, Gregory Vogel, PSM, a Hanwha company.

WORK MANAGEMENT: A proven method for improving operational reliability

By Team-CCJ | April 2, 2024 | 0 Comments

By Rishi Velkar and Todd Robison, NV Energy

Combined-cycle plants built during the construction boom of the late 1990s/early 2000s are now about 70% through their 30-yr design lives. Although not originally designed to cycle, ever-increasing amounts of solar energy readily available on the grid, especially in the Southwest, make it economically prudent for these plants to cycle off completely from time to time throughout the year.

However, cycling and plant age contribute to premature equipment failure, negatively impacting reliability and increasing operating costs. It’s important for plant personnel to be proactive to properly address issues affecting availability and avoid outages of long duration.

The following case history concerns NV Energy’s Chuck Lenzie Generating Station, a 2 × 1 natural-gas-fueled combined cycle located about 30 miles north of the Las Vegas Strip. The plant has two power blocks, each equipped with two 7F gas turbine/generators and one D11 steam turbine/generator.

Lenzie, which went into service in 2006, achieved an equivalent availability factor (EAF) of 98.6% in 2023, its highest ever. While the number of starts doubled from about 63 per turbine in 2022 to more than 140 per turbine in 2023, the Lenzie team was able to reduce the plant’s forced-outage hours to only 153 compared to more than 1000 hours from the prior years. This was achieved primarily because of Lenzie’s strong adherence to NV Energy’s work management policy/practices (figure).

Recall that the primary purpose of work management is to recognize, define, prioritize, and document the maintenance effort required to restore and preserve system function for reliability. Work identification encompasses both reactive (corrective) and proactive (preventive) work and requires cooperation between the operation and maintenance staffs. The outcome is quality work that improves plant reliability and availability.

Process plants typically have a Computerized Maintenance Management System (CMMS) incorporating work orders that can build up over time if not properly maintained. Lenzie started 2023 by reviewing, with representatives from both operations and maintenance, each work order in backlog.

Result: The backlog of corrective maintenance orders was reduced from 600 to 120, the preventive work orders from 100 to 20. Note that NV Energy refers to a storage place for work orders that have not been closed as “The Backlog.”

An accurate Backlog is necessary to continually evaluate maintenance requirements and successfully perform work planning and scheduling activities. Duplicate work orders, and jobs that had become irrelevant or impractical, were purged from the Backlog; they divert attention from real priorities and make it impossible to accurately gauge the workload.

The next step in the work-management process is a critical one involving the work planning done by way of scheduling software. Work scheduling is the process of work management that enables the plant to improve the effectiveness and efficiency of the maintenance effort by doing the right work at the right time using the right resources.

The process of work scheduling is essentially determining the when and who of the work-management process by prioritizing the work backlog and then matching it to the available resources. This is conducted using the principle of joint prioritization—the collaborative prioritization of work among key stakeholders.

Another critical piece of the puzzle is to maintain the Short Notice Outage Workorder list (SNOW), a list of work orders that take an outage to complete. It is vital to plan the work in advance so when an opportunity presents itself during an outage, forced or planned, the work can be completed, not put off until the last minute. At Lenzie, the SNOW list is reviewed and modified/updated multiple times annually.

However, the most important practice that a powerplant should adopt is to have constant communication between its operations and maintenance organizations. Since operations is the most important customer at any plant, it is the eyes and ears in the field and the first alert to issues. But these must be communicated to maintenance and it is vital for management to provide a platform to support these discussions. At Lenzie knowledge is transferred during the morning meeting at 6:10, after the shift change. This is where operations makes maintenance aware of any issues that present a reliability risk.

Also, as power companies plan to retrofit and upgrade legacy equipment and processes as plants approach end of life, one topic often left out of the discussion is the importance of stocking critical spare parts. Having critical spares on hand can reduce downtime significantly. During 2022-2023, Lenzie personnel identified and stocked more than 200 spare parts in the warehouse.

Finally, keep in mind that Lenzie was able to exceed its EAF goal by adopting a proactive maintenance approach. Given that combined cycles likely will be cycling more in the future, this might be a good time to review your plant’s mode of operation and method of maintenance planning.

Air-Cooled Condensers: ACCUG 2023 Conference Recap

By Team-CCJ | April 2, 2024 | 0 Comments

The 13th annual meeting of the Air-Cooled Condenser Users Group (ACCUG) was held June 20 – 22 (2023) at Dominion Energy’s offices in Glen Allen (Richmond), Va. Strong international participation, interaction, and discussion enhanced the benefit of this event to all ACC owner/operators, service providers, and technical consultants worldwide.

The presentations discussed below, which focus on chemistry and corrosion, design and performance, and operation and maintenance, are available at acc-usersgroup.org. The next meeting of the ACCUG will take place in London this July. Registration is now open.

Chemistry and corrosion

Barry Dooley, Structural Integrity (UK) and conference co-chair, opened the conference with a backgrounder on ACC corrosion and cycle chemistry, stating that flow-accelerated corrosion (FAC) damage to ACCs is the same worldwide with all chemistries and plant types. This led to a discussion of global ACC inspections and common indicators of both single- and two-phase FAC, and a review of the phase transition zone in the LP steam turbine.

Dooley included details on corrosion damage and analysis, and a reference to document ACC.01, Guideline for internal inspection of air-cooled condensers, available at no cost on the user group’s website.

He concluded with an update on film-forming substances, and various technical guidance documents for plants with ACCs, available at www.iapws.org, and also free of charge.

Andy Howell, EPRI and conference co-chair, then examined ACC steam-side finned-tube corrosion downstream of tube entries. He focused on “new information, and a new investigation.”

Howell began with erosion and corrosion of carbon steel in the LP turbine exhaust contributing iron oxide to the condensate, which would impact the surface of the ACC heat exchanger tubing (Fig 1).

More evidence of metal loss typically is found in the ACC steam distribution upper duct and at the tube entries (Fig 2). Metal-loss drivers are velocity and corrosion. At the tube entries, turbulence (velocity) is the highest, and the initial steam condensate is the most corrosive (lower pH).

Observations in 2022 identified metal loss downstream of the tube entry (Fig 3). This is the new information and investigation. Previously, industry focus was on the tube-entry area, and downstream corrosion had not been widely investigated or reported.

So, what are the implications of this down-tube corrosion? According to Howell, investigations are important because:

  1. This may be a major source of iron transport to the steam cycle.
  2. There is potential for tube leaks (air in-leakage).
  3. Investigations will help clarify whether all ACCs are susceptible and may provide more opportunities to reduce metals transport throughout the steam cycle.

Dooley then returned with a detailed look at film-forming substances, focusing on the latest international activities. For more on this topic, see FFS: Sixth International Conference, CCJ No. 75, p 75.

Sam Dunning, Virginia City Hybrid Energy Center, next offered a plant experience report on air in-leakage. Dominion Virginia Power’s VCHEC features two circulating fluidized-bed boilers and one 610-MW turbine/generator, commissioned in 2012. Fuels are waste coal and biomass.

The air-cooled condenser, by SPG Dry Cooling (formerly SPX), contains 10 streets of six bays each, with 36-ft-diam fans. Steam jet air ejectors remove non-condensable gasses from the ACC. Hogging ejectors are used to evacuate the ACC and dual-stage holding ejectors are used for normal operations.

Following a 2021 outage, VCHEC was dispatched to full load. Operators noticed that when switching from hoggers to holding ejectors, backpressure was not maintained. Hoggers were returned to service.

Typical air in-leakage indicators suggested a major leak in the ACC. The energy center was derated by 200 MW for two days and by 100 MW for five days. Troubleshooting, including use of all typical methods of leak detection, met with no success.

Then, a large leak was found in the hogging-ejector isolation valves. It allowed air to be pulled back into the discharge side of the out-of-service hoggers. Said Dunning, “inspection of the valve internals showed the rubber (EPDM) seated valves had lost more than half of their seals” (Fig 4). The rubber had become brittle and the adhesive used to hold the seal in place had deteriorated. Other valves were checked and all were experiencing the same failures.

Valves were replaced in-kind for operations, and later replaced with metal-seated ones.

Dunning’s observation and recommendation: The seat design of the rubber-lined seal limits the rating level of vacuum valves. High-performance butterfly, including triple offset styles, should be considered. He added that “if rubber-seated valves are currently in vacuum service, periodic inspections should be conducted more frequently as the valves age.”

Design and performance

Carlo Gallina, Cofimco (Italy), presented FRP-carbon twin shaft for axial fan blades. Said Gallina, “research and experience showed the need for an improved shaft to connect the blade airfoils to the hub. This led to the pultruded FRP-carbon twin shaft to improve the blade load capacity of large fans in both ACCs and cooling towers.”

He reviewed the basics. Lift must be generated for each blade, but varies because of aerodynamic disturbances—including mechanical obstacles (walkways, etc), wind gusts, and fan location within the ACC. Bending moment and lift are transferred to the hub, drive system, and structure, all influenced by the varying loads.

“Therefore,” he explained, “the blade connection to the hub must be strong enough to withstand high loads generated at the shaft.”

Rigid solutions transmit loads to the structure and can cause vibrations. “Using pultruded FRP-carbon shafts gives the blades suitable flexibility, and reduces vibration. Plus, the high strength of carbon limits blade deflection.” Plus, plus, the natural frequency of these blades is far from typical fan forcing frequencies.

Next, Gallina introduced the Cofimco twin shaft for axial fan blades featuring a “binocular shape” (Fig 5, right). He then reviewed full details of work at Cofimco’s test rig complex in Italy. Conclusions:

  • The twin-shaft blades can withstand severe duty points and manage high, abrupt loads.
  • Blades generally can be operated from zero to 100% speed when driven by a VFD.
  • Vibrations and loads introduced to the structure are greatly reduced.

Huub Hubregtse, ACC Team (The Netherlands), discussed Common performance problems for ACCs. “In general,” he began, “there is a lack of technical knowledge by operators, and many ACCs have performance problems, especially in summer. Not all operators have enough knowledge of the processes to analyze the system.”

He outlined and discussed the primary impacts on performance:

  • Fans in respect to air flow and static pressure.
  • Recirculation of hot air.
  • Fouling.
  • Steam distribution in heat exchangers.
  • Leaks.
  • Noise (indirectly).

Static pressure reduces air flow and increases motor power requirements. He discussed fan measurement criteria for air flow, static pressure, and absorbed power.

“Recirculation means hot air from the top is sucked down to the fan inlet, resulting in warmer air for cooling,” he explained. The main cause is the difference in suction pressure at the fan inlet and the pressure at the outlet of the ACC. This can be caused by a nearby building, wind, or other factors. To check this, he suggests measuring air temperature in the plenum and air temperature at a distance.

“Fouling from dust, seeds, and insects can obstruct the space between the tube fins, resulting in higher static pressure and less air flow,” he continued. Most fouling can be removed with high-pressure washing (1300 to 1600 psig). Other fouling can be difficult and require blasting with sodium bicarbonate or similar method. “The performance impact of cleaning can be enormous,” he offered.

Hubregtse continued: Steam flow through the ACC heat exchangers is controlled by the small (15 mbar) pressure difference between inlet and outlet. Flow reduction causes can be fouling, vacuum pumps, or layout of the suction piping. Testing with thermal imaging should reveal the problems.

Imaging can show low pressure differentials in the middle of the tubes, for example. The suction processes will take vapor/steam before they take air. If there is a leak, air can penetrate the system, blanketing the inside of the finned tubes. A simple vacuum drop test can indicate leak rate.

But finding the leak can be difficult. “The most common and reliable way to find leaks is to spray helium gas near a suspect location and test the ACC for helium in real time. Helium testing can be expensive (and time-consuming), but is reliable,” he explained.

Although noise is not directly related to performance, “some operators reduce the speed of the fan when noise is a concern,” he noted. If this occurs, “the blade angle has to be increased to compensate for the loss of air flow.” One danger is that the fan can go into stall, reducing the air flow.

Keith Paul, EPRI, followed with Infrared drone inspection of an air-cooled condenser to analyze heat distribution. The subject site was New York Power Authority’s Zeltmann Power Project, a 576-MW, 2 × 1 7F-powered combined cycle in Astoria, NY, commissioned in 2005.

Before the site visit, drone calibration runs were conducted at Evapco Test Labs in Maryland. “We ran the same drone, tested camera resolution and distances, and tested air in-leakage detection with intentional in-leakage.”

His conclusion: “Based on our experience at Zeltmann, and at Evapco’s test lab, we cannot say that drone infrared inspections provide definitive leak-detection services. This is still a work in progress.” The site switched to still cameras.

On the positive side, initial results at Zeltmann allowed the plant to focus on specific sections for possible repairs in an upcoming outage.

“EPRI is now developing a test methodology to use acoustic cameras mounted on a drone to inspect air-cooled condensers,” Paul explained. This is based on success with handheld acoustic cameras. This ongoing drone work is a potentially strong time-saving technique.

Hector Moctezuma, Valia Energía (Mexico), offered an Update on a hybrid cooling retrofit installation, first presented to ACCUG in 2014. He spoke first about the plants in his country.

“Plants are often not able to reach maximum output during summer due to high steam-turbine backpressure from the main condenser, which limits use of duct burners and sometimes means reducing CT output to avoid a steam-turbine trip,” he said.

More specifically, “This significant power output reduction is due to ACC under performance in summer and with windy conditions.” ACCs have also experienced physical degradation through the years, mainly severe fouling and tube damage.

“With the help of SPIG USA, a parallel condensing system (PCS) was chosen in which exhaust steam is simultaneously condensed in both a wet evaporative and the existing dry cooling system” (Fig 6).

“The goal is to remove the steam-turbine backpressure limitation during all periods with ambient temperature higher than 86F (1000 hours per year) by adding enough wet cooling capacity to the existing 32-cell ACC.”  The design considers local water limitations.

The speaker reviewed results for the nominal 500-MW Unit IV at Rio Bravo Energy Park after addition of the wet cooling module in Fig 7. The highlights:

  • Elimination of the backpressure limitation, with a significant sustained improvement of up to 80 mBar (2.36 in. Hg).
  • Power output increase of 20 MW attributed to the condenser pressure reduction and ability to increase condenser load.
  • Heat-rate improvement due to lower condenser pressure (lower backpressure on steam turbine).
  • Power-consumption increase by auxiliaries of about 500 kW for the cooling-water pumps, blowdown and makeup pumps, and cooling-tower fans.

This gives “consistent and repeatable operational reliability under adverse summer conditions after nine years of operation,” he stated.

György Budik, MVM EGI (Hungary), presented on the Hybrid delugable cooler in Dominion’s Greensville CCPP which satisfies the facility’s auxiliary cooling needs using a 50/50 mixture of glycol and demin water. The cooler is located at the opposite end of the plant from the 80-cell ACC (Fig 8).

Hybrid wet/dry coolers like Greensville’s (Fig 9), Budik explained, “offer a dramatic reduction in cooler size relative to all-dry coolers, and, therefore, a significant reduction in civil and maintenance work.” The speaker reviewed some delugable systems installed by his company, including the first such units, which were installed in Iran.

The auxiliary cooler consists of 16 modules arranged side by side, the first five (left side) and the last five (right side) are dry, the remaining six (bays 6 – 11) are capable of deluge service.

Bays have two cooling modules, each with two 12-m-long aluminum cooling elements, best illustrated in the Fig 10 photo. The cooling modules serving all bays are connected in parallel to a common inlet and outlet manifold.

In the deluging bays, sprinkler pipes are installed at the top of the cooling elements, providing a continuous downward flow of water on the external surfaces of the heat exchangers. The Fig 10 illustration explains this.

The operating principle of the deluge system is that partial evaporation of the deluge water keeps relatively cold the rest of the water on the heat-transfer surface, thereby providing additional cooling.

Deluge water is supplied to the heat exchangers from the tank shown in the figure. Water not evaporated is collected in a trough at the bottom of the module. The trough drains to the deluge water tank. A makeup line keeps the amount of water in the system constant. Note that water of good quality is required for makeup, with first-pass RO product acceptable.

Motors driving the deluge pumps are equipped with variable-frequency drives. Operation of the deluge system is not recommended at ambient temperatures lower than 98F, all-dry operation providing sufficient cooling. Use of the deluge system would result in unnecessary water loss from drift, evaporation, and blowdown.

At temperatures above 98F, the number of fans operating in deluge modules are governed according to the following control steps:

  • Step 0: standby, steady state.
  • 1: 12 VFD-controlled fans in bays 6-11 start simultaneously.
  • 2: Front-side fans in bays 1-5 and 12-16 start.
  • 3: Dummy step.
  • 4: Remaining fans in bays 1-5 and 12-16 start.
  • 5: Deluging starts in two bays.
  • 6: Deluging expanded to four bays.
  • 7: Deluging expanded to all six bays (Nos. 6-11).

Note that with Step 7 actuated, design performance conditions are achieved with one fan out of operation.

Next objective for the new hybrid cooling technology demonstrated at Greensville likely is its use in conjunction with dry cooling systems for combined-cycle plants (sidebar). The deluge ACC is touted by its EU sponsors as being the most efficient dry-cooling solution for high peak ambient temperatures. Plus, it is said to resist adverse ambient conditions such as high-speed winds and hot air recirculation.

Other benefits include less auxiliary power consumption, smaller footprint, and lower construction costs compared to dry-only systems. And less water consumption compared to all-wet systems.

ACC with deluge cooling: Not yet, but likely soon

Literature from Enexio Water Technologies GmbH touts Deluge ACC, described in the diagram, as the latest technological achievement in hybrid cooling, where the primary interest is in dry cooling, but where limited water resources are available for use during certain times of the year.

Recall that while dry cooling methods offer an order-of-magnitude reduction in cooling-water consumption compared to wet cooling, overall power-cycle efficiency generally is higher when wet cooling can be part of the solution.

Enexio is one of the consortium partners of the EU-funded Horizon 2020 research and innovation program called MinWaterCSP. Its goal is the development of cooling technologies and water management plans to reduce cooling-system water consumption by up to 95% relative to wet-only cooling systems.

Galebreaker Industrial’s Gary Mirsky presented CFD study of airflow and performance improvement potential. His example was a 2 × 1 plant rated at 578 MW (steam turbine output, 295 MW) commissioned in 2008.

The goal was to increase backpressure trip limits as part of a larger upgrade to increase both gas-turbine output and ACC heat rejection. Another objective: Mitigate wind effects on ACC performance.

The ACC is two units, each with three streets and five cells per street. There are buildings in the immediate area. The best performance solution was a combination of options with both perimeter and cruciform screens.

Operations and maintenance

Mike Owen then presented the latest ACC-related research activities at Stellenbosch University in South Africa. It is home to an active research group specializing in ACC and dry-cooling activities, and is a frequent participant at ACCUG events.

Topics this year included prediction of large-diameter axial-flow fan noise and performance, dynamic blade loading, modeling improvements, machine learning for performance monitoring, and fan drive-train dynamics.

Owen also covered specifics of operation and controls—including air-extraction valves, fan speed range and fan hardware, fan gearbox/motor/VFDs, two-stage air ejectors, drain pot, and pumps. Most of these items would be mentioned during the site tour of Greensville on the last day of the conference.

Jeff Petrillo, Dominion, introduced the group to the Greensville County Power Station with ACC lessons learned. He presented a site overview to familiarize those joining the tour with the facility’s layout and principal equipment. The latter included the following:

  • 80-fan (VFD) ACC with 10 streets (five east, five west).
  • One condensate receiver tank with two deaerators.
  • Four liquid-ring vacuum pumps.
  • Two two-stage steam-jet air ejectors.
  • One drain pot with two pumps.

Jacques Muiyser, Howden Netherlands, presented ACC fan dynamics: Potential problems and solutions. The basis of this discussion: ACC fan blades and/or connection bolts can fail because of high dynamic loads. Muiyser discussed sources and consequences of dynamic/cyclical blade loads, and development work to confirm that a stronger hub design with a more rigid bolt-to-bolt connection can help avoid bolt failure from fatigue.

He began with a refresher course on blade dynamics and mechanical properties, also covering flow distortions attributed to obstructions and crosswinds before moving on to case studies.

In the first case study, owner/operators noticed isolated U-bolt failures at a site. Strain-gauge measurements revealed resonance at high fan speed. Performance measurements then showed the blade angle could be increased while reducing fan speed to avoid the failures while maintaining performance.

In the second case, recurring issues were blade separation at the leading edge, and blade clamping-bolt failures (straight bolts). For the blades, strength was corrected with additional laminate on the leading edge. The clamping bolt issues were corrected by adding a secondary hub ring, connecting all of the clamping pieces.

In Case Three, straight-bolt failures shortly after installation showed signs of failure, primarily at edge cell fans. Root cause was high dynamic loads attributed to winds and high-speed resonance. A modified hub ring was installed to reduce equivalent dynamic loads.

“The hub ring assembly has proven to be an excellent retrofit solution for sites with high dynamic loads. This solution has been tested on site and the design has been refined through testing in the laboratory and numerical simulations,” said Muiyser.

Edwin Houberg, Sumitomo Drive Technologies/Hansen Industrial Transmissions, introduced the Hansen M4ACC gearbox for forced-draft and the Hansen M5CT for induced-draft applications.

The first features mono-block housing, no external piping, and an integrated drywell to reduce leakage risk. One option is a patented mobile brake system to slow down and stop the gear unit during maintenance activities.

The M5CT is a “new right-angle industrial gearbox series dedicated to induced-draft cooling technology,” he explained. This features an extended bearing span with heavy-duty roller bearings for strong shaft support. Numerous instruments and accessories are available.

Jeff Ebert, Galebreaker, then discussed Mitigation of extreme high seasonal winds. His example was a 353-MW gas-fired powerplant in Saskatchewan, Canada, commissioned at the end of 2019. Seasonal winds there can blow at 19 m/s, reducing plant performance.

Galebreaker was asked to determine the best windscreen configuration, height, and solidity to resolve the performance issues.

Ebert described the evaluations and installation that was completed in April 2023.

Various options were considered and material was delivered in October 2022. This was Galebreaker’s first sloped-structure ACC project (Fig 11).

Various tubular products were added for structural support.

Hubregtse returned to discuss gearboxes for ACCs, listing these critical items to include in specifications:

  • Fan shaft power.
  • Power absorbed during worst conditions (during a storm, for example).
  • Inverter installed, variable or direct.
  • Service factor.
  • Lubrication.
  • Vibrations.
  • Temperature range.

A standard service factor, usually between two and three, allows for vibrations, extreme conditions, startup power, and wear. This is also valid for gears, bearings, shafts, and housing.

He also covered thermal power (heat generated inside the gearbox), forces in gearbox, gearbox selection, lubrication, humidity in oil, vibrations, and deformations.

ACC and H20 Best Practices from CPV Valley Energy Center

By Team-CCJ | April 2, 2024 | 0 Comments

CPV Valley Energy Center

Owned by CPV/Diamond Generating Corp
Managed by Competitive Power Ventures
Operated by DGC Operations LLC

680 MW, gas-fired 2 × 1 SGT6-5000-powered combined cycle, located in Middletown, NY

Plant manager: Michael Baier

Overcoming unique challenges to optimize ACC performance

Challenge. At first glance, the air-cooled condenser (ACC) at Valley Energy Center (VEC) appeared to operate efficiently, as designers intended. However, proactive staff analysis revealed performance-robbing subcooling, despite use of a second vacuum pump to compensate for air ingress.

Solution. VEC worked with SPG Dry Cooling to survey the ACC, identify leaks, and perform corrective measures; however, the subcooling remained. Further investigation revealed that increased air flow across the heat-exchanger bundles, paired with slight air ingress, was driving the subcooling anomaly. Although the system’s design backpressure, temperature, and steam load were in sync, more fans than required were operating. Further investigative work, found that the DCS logic prevented the fans from turning off to counteract the subcooling.

DCS logic. The ACC was operating at 2.0 in. Hg Abs, but the deadband within the logic required the pressure to reach 1.91 in. for 10 minutes to allow the control logic to adjust fan steps and reduce air flow. Several things were found that did not permit the ACC to drop to the required pressure for the prescribed duration, including the following:

  • The vacuum system was designed according to specifications developed by the Heat Exchange Institute for ACCs, with a minimum design suction pressure of 1.0 in. Hg Abs. The steam path through an ACC is several hundred feet long, and the associated pressure drop can range from 0.5 to 1.0 in., putting the capacity of the vacuum system near the 2.0 in. setpoint (as measured at the ST exhaust).
  • The air ingress persisted, spreading throughout the ACC, and limiting its cooling capacity. Conceptually, 1 ft³ of atmospheric air expands to 15 ft³ under vacuum, occupying volume intended for steam condensing.

The limitation of the vacuum system and persistent air ingress prevented the ACC from overcoming the deadband. It eliminated the control logic’s ability to adjust and optimize parasitic power alongside the backpressure. With the assistance of SPG, VEC made minor adjustments to the deadband and setpoint and reduced parasitic power by nearly 3 MW while maintaining the required backpressure. The improvement was achieved by turning multiple fans from full speed to half speed (reducing the required power per fan by seven-eighths) and eliminating the need to run a second vacuum pump. Additionally, VEC improved its overall heat rate by reducing subcooling and parasitic power consumption.

Note that the subcooling issue was unique to the time of year when ambient temperatures were between 35F and 75F. VEC operates approximately 5000 hours within this temperature range, resulting in a loss of approximately 15,000 MWh/yr prior to the new ACC logic implementation.

Results. VEC’s experience highlights the importance of investigating all aspects of ACC performance to optimize efficiency. As a result of this improvement, VEC will implement SPG’s remote performance monitoring system (ACC360) to maintain the realized results and continually improve the ACC system.

Project participants:

McKenzie Slauenwhite, plant engineer
Thomas Viertel, maintenance manager
Dave Engelman, operations manager
Efrain Morales, lead shift operator
Ernest Hill, lead shift operator
Bob Arraiz, lead IC&E technician
Daniel DeVito, IC&E technician

Closed-cooling-water-system upgrade saves money, improves safety

Challenge. If VEC lost station power, both pumps serving the closed cooling water (CCW) system would lose their power supply. Note that the power draw is too great to supply the pumps from the essential-services bus.

Were station power lost with the pumps in service, the flow of water to the steam-turbine lube-oil cooler (LOC) would stop. To mitigate this risk, a diaphragm pump was installed to maintain the required lube-oil temperature for turning-gear operation.

However, a challenge associated with the diaphragm pump is the amount of plant air required for its operation. Plus, the plant air compressors also are not on the essential services bus, which meant VEC would have to rent a diesel-powered air compressor during loss-of-power events.

Plus, plus, acquiring a diesel-powered compressor in timely fashion during an unexpected loss of station power is less than ideal for a rapid and guaranteed response. Finally, the diaphragm pump’s discharge flow is less than that required by the LOC to meet all possible needs.

Solution. Staff specified a centrifugal pump that maximizes CCW flow through the LOC to assure oil temperature can be maintained as necessary. A spare breaker on the essential-services bus met the power requirement of the centrifugal pump’s motor. Plant verified operation of the new pump during commissioning by using power supplied by the site’s emergency diesel/generator.

Additionally, the CCW discharge lines from the steam turbine’s LOC were tapped and valves were installed in the pump’s discharge and suction connections. Limit switches were added to the valves and brought into the DCS. The plant generated logic that allows the pump to be started from the DCS with the limit switches being a start permissive. Lastly, an HOA (hands off auto) switch was added to the pump’s motor breaker to allow manual operation.

Results:

  • Increased safety: For example, less chance of steam-turbine damage caused by high lube-oil temperature.
  • Eliminates the need to rent a diesel-driven air compressor on loss of electrical power.
  • Fewer steps to put a pump in service during an emergency.

Project participants:

Thomas Viertel, maintenance manager
Bob Arraiz, lead IC&E technician
McKenzie Slauenwhite, plant engineer
Daniel DeVito, IC&E technician
Liam Collins, maintenance mechanic

HRSG Forum 2023: EPRI Technology Transfer Workshop

By Team-CCJ | March 12, 2024 | 0 Comments

Steven C Stultz, Consulting Editor

Editor’s note: Registered users can access the comprehensive slide deck developed by EPRI for its HRSG Technology Transfer Workshop, go to www.powerusers.org, click the HRSG Forum logo and then the “Conference Archives” button at the top of the screen.

As a final day attached to the HRSG Forum’s 2023 Conference and Vendor Fair, June 12 – 15, at the Renaissance Atlanta Waverly, the Electric Power Research Institute presented EPRI heat-recovery steam generator technology transfer day, open to all Forum attendees.

Principal organizers were these EPRI program leaders:

  • Bill Carson, HRSG.
  • Tom Sambor, Power Plant Piping.
  • John Siefert, Materials.

Primary agenda topics included the following:

  • Current industry challenges.
  • Safety issues with header end caps.
  • Activities with high-temperature components.
  • Steam leaks in high-temperature intersections (tees).
  • Damage related to attemperators/desuperheaters.
  • Activities with low-temperature components.

Bill Carson opened the program with a safety session on personal protective equipment, followed by an overview of information available through the EPRI website. Those interested should visit https://enroll.epri.com.

Eugene Eagle, Duke Energy, the utility chair of the HRSG program, then presented an overview of EPRI Program 218, Heat-recovery steam generators, and research areas that include damage mitigation, improved performance, life management, flexible operation, and HRSG innovations. He included specific values gained from EPRI Program technology research activities. For more details, visit Program 218: Heat Recovery Steam Generators | Program Home (epri.com)

Today’s challenges

Tom Sambor offered an interesting assessment of the state-of-the-industry, and summarized HRSG infrastructure challenges (table), stating “Uncertainty is increasing; resources are decreasing.”

Sambor focused on the increasing need for an “integrated life-management” strategy, which EPRI has organized into seven parts. An integrated-life management approach for a component relies on, at a minimum, an equivalent consideration of mechanics (structural analysis, thermal hydraulics, etc), metallurgy, and nondestructive evaluation.

EPRI has numerous examples where each of these elements, he stated, are performed “poorly” by power generation service providers as they frequently lack a “rigorous approach.” See “Integrated Life Management of Grade 91 Steel Components: A Summary of Research Supporting the Electric Power Research Institute’s Well-Engineered Approach” for free download.

Sambor then reviewed how EPRI has a suite of information available for HRSGs that fits within each part of an integrated life-management strategy in detail.

Fundamentals. The “industry is reliant on NDE as the only tool in the toolbox,” despite industry codes and standards emphasizing the importance of materials testing and engineering evaluation, Sambor stated. He referenced a series of documents that the HRSG program at EPRI has on fundamentals, increasingly important because of the loss of both service-provider expertise and engineering and support staff within utilities.

Service experience. Sambor explained how the examination of unexpected, premature, or early-in-life industry failures has led EPRI to identify some components or systems as systemic “industry issues.”

Specifically, attemperators/desuperheaters, flat end closures, seamless and welded intersections, stainless-steel flowmeters, seam welded fittings/piping, small-bore DMWs, and, more generally, CSEF steels were all identified as industry issues relevant to HRSGs.

He identified that flat end closures, intersections, and attemperators/desuperheaters would be discussed as part of the day-long technology-transfer meeting because there have been recent and historical examples for each identified issue. See “Life Assessment Primer for Heat Recovery Steam Generator Internal and External Piping.”  

Specifications. Sambor next noted the increasing need for specifications that go above and beyond the minimum requirements in relevant HRSG codes and standards. Emphasizing this need is the fact that the previously discussed industry issues are typically associated with components that comply with the ASME Code.

To that end, EPRI has developed a range of guidance initiatives that includes product forms, processes, components, and plants. Sambor further explained that “EPRI is uniquely positioned to provide comprehensive technical assistance for material/component replacement or new construction,” including specification guidance.

Guidelines. Sambor then reviewed numerous guidelines focusing on strategies to avoid pressure-part failures—including those during startup and shutdown, HRSG materials selection, and operating HRSG drains, etc. He highlighted the need for reducing uncertainty and pointed to additional information available for that purpose.

NDE and FFS. Interesting discussions followed on nondestructive evaluation and analysis. Showing large-feature cross-welds in Grade 91 material, Sambor stated that there is “limited detectability of creep damage in modern alloys via NDE.”

He also stated that “NDE alone is not an adequate life-management strategy. Mechanics and metallurgy (at a minimum) must be considered, and the uncertainty in these areas needs to be reduced as much as practical.”

Further support for this statement: “A significant portion of the costs to perform NDE is for no-value-added activities such as scaffolding, insulation removal, surface preparation, and project management,” he explained.

He also addressed fitness-for-service (FFS), noting that EPRI has a large ongoing effort in this area. FFS methods developed as part of this work are being used for tees and other geometries. EPRI also has the capability, in its lab or otherwise, to subject components removed from service to post-mortem evaluation and analysis. See “An Informed Perspective on the Adoption of Comprehensive Fitness-for-Service in an Integrated Life Management Strategy.”  

Repair or replace. Decisions can be difficult, and repairs are “typically not one-size-fits-all.” Each needs to be engineered, but more critical is the determination of root causes. “Root causes must be identified and mitigated,” he said.

Sambor offered an extensive list of information that is available to assist in repair/replace decisions. Subjects include weld overlay, tube and tube-to-header repairs, steam turbines, fans, and deaerators. Another long list focuses on CSEF steel alternative weld repair and includes effects of filler metal or process, weld geometry, and other component specifics such as girth and dissimilar metal welds.

After outlining a multitude of research programs and results, Sambor stated that “research is not complete. EPRI continues to assess repairs on materials removed from service,” and encourages owners/operators to donate samples.

Technology transfer. Sambor concluded this section of the program stating that EPRI technology transfer includes numerous activities that are publicly available, such as:

  • EPRI presentations at industry workshops.
  • Participation in codes and standards.
  • Published papers and articles to raise awareness.
  • Industry alerts. See example here.

He then said that “Technology transfer is not a one-way street. Reach out to EPRI if you have experienced and/or identified a unique failure or have a question” (email ppa@epri.com).

New construction challenges

With modern gas turbines, exit gas temperatures of 1150F and steam temperatures of 1050F are exceeding the practical limits for Grade 91 steel (Fig 1).

So, the question becomes: “Do you (the owner/operator) opt for advanced stainless/higher chrome CSEF steels, or push the 9Cr performance envelope?”

Advanced alloys offer options, but also some learning curves. For example, there could be options when transitioning from stainless steel to CSEF steel within the HRSG (Fig 2). The transition shown could be in the piping (Option A) or in the tubing (Option B).

Said Sambor, “EPRI is aware of steam leaks or failures in each case” (Fig 3).

   

There are similar issues with tube oxidation/exfoliation (Fig 4).

Basically, care must be taken because modern gas turbines could be “abusing the HRSGs,” cautioned Sambor.

Header end caps

John Siefert next took the stage to discuss the state of knowledge and screening methodologies for header end caps, a growing industry safety concern. Flat-end closures are used in many HRSG headers primarily for their space-saving design (Fig 5). See “Life Management of 9%Cr Steels—Assessment of Header End Cap Geometries.”

While surface stresses can be high during startup and shutdown, which may lead to fatigue damage, the state of stress in the weld during normal operation also makes end caps susceptible to creep damage. EPRI is aware of failures attributed to both damage mechanisms. It is impossible to know if a failure is caused by fatigue or creep without a rigorous and integrated analysis of the root causes.

Case studies show that failure incidents are not new, and a few “catastrophic failures” were reviewed where the end cap was ejected without warning.

Siefert discussed the various end-cap designs and design rules, typical creep redistribution stresses, and cyclic operation thermal stresses, material chemical analyses, and typical inspection techniques.

EPRI’s recommendation is to implement an integrated life-management plan that considers the following:

  • Geometric configuration (including fabrication quality).
  • Design margins (excess thickness, for example).
  • Operating conditions (temperature imbalances and transients).
  • Metallurgy and risk (deformation and damage susceptibility).
  • Access for inspection, including where resulting damage is likely to occur.
  • Lifetime predictions.
  • Consequences of failure including plant operations and personnel.

Recent activities

Sambor returned to the podium to review the global installation totals for 9Cr steels, both Grade 91 and Grade 92. The totals include more than 1000 supercritical and ultra-supercritical steam systems and more than 2600 combined cycles installed globally in the past 25 years.

Several factors, including material ductility, can compound and increase the risk to rupture for these materials (Fig 6).

Two interesting points:

  • For most of the ASME Boiler and Pressure Vessel Code’s existence, the use of ductile materials has largely protected the industry from widespread creep concerns in the high-temperature regime.
  • If materials are to be classified by Section II as possessing low creep ductility, then an optimized set of design rules should be invoked by Section I to responsibly design safe structures, as there is no explicit design life.

Noted Sambor, “The thrust behind Grade-91 Type-2 composition was to reduce the future population of low-ductility heats.”

After reviewing Code Case 3048, Design rules for CSEF steels which are creep intolerant for construction (May 4, 2022), he summarized: “Extensive challenges remain to improve design rules for complex materials, structures, and operating modes.”

He then presented a recent case study of a reheater tube-to-header failure to emphasize the importance of rigorous analysis. Sambor recalled that he once shared photos of the failure with several individuals and asked their opinion on what caused the failure; all were quick to attribute the failure to fatigue. He then showed various metallographic sections of the failure, all of which illustrated that the failure region was “loaded” with creep damage, indicating the failure was due to creep rather than fatigue.

The importance of this determination, Sambor emphasized, is that the utility/plant now is aware of a systemic problem (attributed to component configuration and operating conditions) rather than a one-off failure.

He finished off the discussion on high-temperature components with a presentation on new efforts towards online creep and fatigue damage trending of HRSG components and the development of various web-based calculators available through EPRI.

Tee intersections

Siefert returned to discuss another Safety Alert for steam leaks in high-temperature intersections, specific to tees.

An EPRI Industry Alert, Seamless tee intersections, was issued February 2023, suggesting that a single unit generally may have four to eight at-risk tees.  See Fig 7 for terminology. Discussions covered damage mechanisms, design, fabrication, operation, and metallurgy.

The damage mechanism discussion concluded that all the tee steam leaks to date could be attributed to the creep mechanism. Siefert emphasized that external metallurgical laboratory evaluation has also reached that same conclusion.

One reason for creep-related failures associated with these tees is inadequate design requirements, which may result in a lack of reinforcement and/or significant variability between supposedly identical tees.

In terms of fabrication, Siefert highlighted that the steam leaks “do not suggest gross issues linked to shop or field post-weld heat treatment,” which is a common concern with CSEF steel material. He instead identified a case where a tee crotch weld repair was performed and another case where a vee shape was roughly machined into the ID surface of the tee crotch, both fabrication issues that have affected the lives of tees.

Operation discussions summarized that units with tee steam leaks have all been operating within their design envelope (that is, operating below their design temperature/pressure), and summarized analyses that EPRI has performed to determine if cyclic operation (fatigue) is a concern.

For one case study analyzed, there is no evidence that the inelastic strain range calculated during cyclic operation would result in fatigue cracking within the number of cycles the tee has experienced, and there was no evidence to support ID-initiation for any of the observed damage.

Siefert finished the tee discussion on the topic of metallurgy, where he detailed a recent failure that is the first reported tee steam leak in a Grade 22 system, which means that this industry issue is not isolated to only CSEF steels. He also highlighted a case study where a tee was found to be the incorrect alloy, X20 rather than Grade 91, and emphasized the importance of positive material identification (PMI) on tees in the field for this reason.

Finally, Siefert emphasized the importance of metallurgical risk on CSEF steel tees by illustrating how the time-to-creep crack initiation could decrease by a factor of 10 because of increased metallurgical risk.

Attemperators/desuperheaters

Sambor covered common approaches for diagnosis and mitigation of attemperator damage issues using historian data, instrumentation, metallurgical analysis, and operating data.

In his first example, he illustrated how a review of historian data revealed “several easy to identify, detrimental phenomena occurring.” Further, he explained how historian data can be used to perform an energy balance around the attemperator to determine if a detrimental condition exists, and mentioned that EPRI has a tool available for doing so.

In a second example, Sambor emphasized the importance of adding surface-mounted thermocouples at select locations upstream and downstream of attemperator piping for improved attemperator diagnostics. He showed how, in one case study, the historian data did not indicate an issue with the attemperator, but thermocouple data on the downstream elbow did reveal that relatively cool spray water was impinging on the relatively hot piping, which is a thermal fatigue concern that has resulted in steam leaks.

Since a concern with adding more thermocouples often is how to collect the data, Sambor mentioned that EPRI has developed a low-cost data logger for doing so. Finally, he emphasized that some issues with attemperators could be associated with less-than-ideal operational strategies, such as trying to roll the steam turbine with a too-high gas-turbine exhaust gas temperature.

Sambor finished the topic with a recent bypass desuperheater case study that involved laboratory evaluation and an analysis of plant operating data. He highlighted how easy it has become to analyze what he labels “big-data” from the plant (data evaluated was for dozens of tags at one-minute intervals for a calendar year) and the importance of doing so; the operating data he illustrated revealed the same detrimental patterns occurring for most startups and shutdowns, rather than just the occasional occurrence.

Low-temperature components

Sambor finished the day by leading a discussion on HP drums. Based on the comments made by attendees, it was clear that additional technology transfer around integrated life-management strategies for drums was necessary. This will be included in a future HRSG Forum event.

HRSG Forum 2023: Cycle Chemistry and FFS Workshop

By Team-CCJ | March 12, 2024 | 0 Comments

Steven C Stultz, Consulting Editor

Barry Dooley, Structural Integrity Associates (UK), opened the Cycle Chemistry Workshop on Day One of the HRSG Forum’s 2023 Conference and Vendor Fair, June 12 – 15, at the Renaissance Atlanta Waverly, with Film-forming substances for combined-cycle/HRSG plants: History, background, and needs.

He first presented IAPWS nomenclature background for film-forming substances (FFS), made up of two categories:

  • Film-forming amines/amine products (FFA/FFAP).
  • Proprietary non-amine-based film-forming products (FFP).

Most experience to date, he explained, is with the first category. Dooley then gave clear visual representations on FFA chemical structure (Fig 1) and the common topic of hydrophobicity.

One overall caution came early: “Dancing water balls,” he explained, “are thought to indicate protection, but we now know that hydrophobicity does not necessarily mean protection” (Fig 2). This would be explained further with examples, such as Fig 3. In these conventional subcritical-plant reheater tubes, the example on the left was dosed with a non-amine FFP. The example on the right was never dosed with any FFS.

Dooley clarified that “It is unclear if hydrophobicity is a key aspect of corrosion control. In solution, some FFAs can actually be hydrophilic and increase surface wetting.”

This message reinforces the complicated nature of simple visual assumptions.

Detailed FFS background is available in Film-forming substances: Sixth International Conference, CCJ No. 75, p 75, and A wakeup call on film-forming substances, CCJ No. 60, p 12.

One important presentation takeaway was the list below of “Key highlights from fossil and combined-cycle/HRSG FFS applications”:

  1. There are universal reductions (measured) in feedwater Fe and Cu transport, but “no equivalent understanding” of the mechanisms of oxide growth reductions.
  2. There are general (visual) observations of hydrophobic films on water-touched surfaces, but “it is underlined that hydrophobicity does not prove presence of a film or any protection.” Refer back to the sketch of control angle in Fig 2.
  3. There is generally good shutdown protection of water-touched surfaces.
  4. Film formation remains “very questionable” on steam-touched surfaces.
  5. Studies of adsorption of film onto metal surfaces as a function of FFS hopefully will provide information for changing the FFS applied.
  6. Arresting flow-accelerated corrosion (FAC) is difficult to “see” other than by reduction of iron. Air-cooled-condenser corrosion/FAC is the exception. See report ACC.02: Guidelines for internal inspection of air-cooled condensers, available at no cost on https://acc-usersgroup.org
  7. There are FFS application problems reported in some plants worldwide: internal deposits, tube failures especially under deposit corrosion, formation of “gunk” (gel-like) deposits in drums and on heat transfer surfaces, in steam turbines, and strainers/filters. Dooley offered detailed examples.

Looking forward, Dooley outlined the “path to needed research.” Clarifying first that most work to date has been with metal surfaces rather than oxide surfaces in operating plants, Dooley highlighted the need for fundamental work on the “effect of FFS on growth mechanisms of Fe, Cu, and Cr oxides in water and steam.”

Similarly, “much work is needed in the future on the effect of a wide range of FFS additions to allow more rugged and permanent advantages such as the ability to change from one FFS to another.”

Current activity and discussion are the pathway to an IAPWS Certified Research Need (CRN) by the International Association for the Properties of Water and Steam Power Cycle Chemistry Group.

In summary, he stressed application of two key rules, as the industry awaits a more complete understanding:

Rule 1, Make sure plant chemistry is optimized before application of an FFS.

Rule 2, Conduct a comprehensive review before any FFS application. Refer to IAPWS TGD8-16 (2019), Application of film-forming substances in fossil, combined cycle, and biomass powerplants, in particular Section 8, available gratis at http://iapws.org.

Doug Hubbard, retired manager of Chemical Engineering at American Electric Power, followed Dooley with Do you need a film-forming substance? How do you know?

He discussed corrosion protection during layup conditions, outlining AEP’s guidelines to stop offline corrosion. Principal AEP options are:

  1. Dry layup: Completely remove and keep all water and moisture off metal surfaces (ideal relative humidity: below 40%).
  2. Use FFS to keep water from coming in contact with metal surfaces.
  3. Wet layup: Remove and keep all oxygen out of water. Use nitrogen blanket.
  4. Keep fluid moving.

These are in order from best to worst, but “any one of them is better than doing nothing,” stated Hubbard. He also reviewed “layup stumbling blocks,” such as on-line schedule uncertainties.

He then covered standard “corrosion protection during operation,” citing the IAPWS limits for total feedwater iron:

  • Economizer inlet OT < 1 ppb (actual, optimized < 0.5 ppb).
  • Economizer inlet AVT (O) < 2 ppb (actual, optimized < 0.5 ppb).
  • Economizer inlet AVT (R) < 2 ppb (actual, optimized < 2 ppb).

One basic test shown for iron is the Millipore: snow white should indicate optimized corrosion protection (Fig 4). Said Hubbard, “I have never seen Millipores snow white and total iron not meeting IAPWS limit.”

So, the question on need for FFS remains.

He then offered some “experienced-based opinions:”

  1. Layup protection:
  • If capacity factor is below 15%, FFS will not have time to “film cycle.”
  • If capacity factor is above 60%, FFS could be too expensive to feed.
  • If unit runs hard and is then down for a long period of rime, this could be an ideal use of FFS.
  1. In-service corrosion protection:
  • FFS is not needed for AVT O/OT units.
  • If there is significant two-phase FAC, FFS could be part of the solution once cycle chemistry is optimized.
  1. Failure mitigation with FFS:
  • Good option for pitting attributed to oxygenated stagnant water.
  • Unclear for pitting due to chloride/sulfates.
  • Unclear for under-deposit corrosion.
  • No known value for existing corrosion fatigue (driven by strain).
  • However, if you are trying to prevent corrosion fatigue, FFS may be of value by slowing down the corrosion part of corrosion fatigue.

Hubbard ended with important guidance: “Make sure you define clearly with your FFS manufacturer the goals expected while feeding FFS, with very specific measurables to determine if goals are being met. The FFS manufacturer needs to sign off on these goals and measurables,” he emphasized.

David Little and Bruce Opsahl, Nalco Water, were next with HRSG protection with Powerfilm™ 10000, a non-amine FFS. While outlining the various reasons for considering filming technology, Little emphasized that FFS applications are “not a substitute for a good base steam-cycle chemistry program.”

Nalco introduced Powerfilm 10000 as “a non-amine filming corrosion inhibitor designed to protect powerplant boiler systems from offline corrosion and stresses caused by cyclical operation.”

Little and Opsahl offered a case study of a 2 × 1 combined cycle in north Texas where market-driven layup practices had raised concerns about asset longevity. The plant faced wet layup of the HRSGs for long periods of time. A program was launched to reduce corrosion product transport, measured as total iron, to 5.0 ppb (EPRI action level).

Powerfilm was injected at the condensate-pump discharge. A low continuous dose (0.4 to 2.0 ppm based on feedwater flow rate) was applied during baseload operation, cycling load, and two–shifting on/off with hot standby. A high continuous dose (5 to 10 ppm) was applied for several days prior to shutdown and wet layup (1 month or less) or dry layup.

Using an online laser nephelometer, 3000 iron concentration data points were collected over a four-month period (Fig 5). Filter pad (Millipore) grab samples also were used.

Their summary of results showed that the nephelometer gave economic, portable, real-time collection of iron transport data, and concentrations remained below the target. Also, “iron reduction continued despite increased cycle events of the steam turbine.”

Dale Stuart, ChemTreat, then presented The use of FFA to mitigate corrosion in HRSG units and offered various examples in the US. He said the purpose is to “provide a passive layer when conventional chemistry fails.”

Based on the examples shown, Stuart summarized that:

  1. The FFAs used formed a bonded layer of persistent film.
  2. The FFAs were volatile and traveled through the system.
  3. Treatment was thermally stable, but required increased dosage at higher temperatures because of its higher volatility and desorption coefficient.

Eric Zubovic, Veolia, then discussed the Impact of film forming amines on condenser efficiency concluding that use improves condenser performance by promoting dropwise condensation on the tubes. He concluded that polyamine (FFA) increases heat-transfer efficiency, noting that a continuous feed (at the proper feed rate) is needed to maintain dropwise condensation. He also concluded that “turbine backpressure can be improved between 0.42 and 0.60 in. Hg with dropwise condensation.”

Chris Dumas, Kurita, presented Cetamine® treatment of an HRSG in Spain, a presentation also made at the 2023 IAPWS International Conference on Film Forming Substances. His conclusions: (1) Cetamine G85X is offering beneficial protection during cycling operation and preservation periods. (2) It can be used as an additional treatment to conventional AVT or AVT+PT. (3) It has reduced startup times and use of blowdown. For more detail, see Film-forming substances: Sixth International Conference, CCJ No. 75, p 75.

Many interesting questions and discussions followed these presentations. Topics included good chemistry versus FFS in a new baseload plant, FFS selection for cycling units, iron sampling processes including filters, methods of pH control, and FFS versus changes to materials.

Dooley’s Q&A summary: “Excellent questions; we know that many plants do not do their homework before application of an FFS. The pre-application process is the most important, and it is critical to first review IAPWS Technical Guidance Document TGD8-16 (2019),” freely available at www.iapws.org.

Contact Dooley (bdooley@structint.com or bdooley@IAPWS.org) for further information on FFS and the IAPWS FFS conferences.

HRSG Forum 2023: Welding and Metallurgy Workshop

By Team-CCJ | March 12, 2024 | 0 Comments

Steven C Stultz, Consulting Editor

The afternoon workshop on Day One of the HRSG Forum’s 2023 Conference and Vendor Fair, June 12 – 15, at the Renaissance Atlanta Waverly, focused on welding and metallurgy. It was a combined effort among Jeff Henry and Kevin Hayes, Applied Thermal Coatings, and Amy Sieben, Industrial Air Flow Dynamics (IAFD) and had the official title Powerplant materials, welding, and welding engineering support: What the industry-wide loss of expertise means for plant owners and operators.

Henry began with what a recent failure suggests about the state of our industry. It concerned the failure of a 10-in.-diam tee after 80,000 hours of service (Fig 6). The component, from a 635-MW coal-fired boiler producing steam at 3700 psig/1050F, suffered a through-wall crack at the crotch position on one side of the tee, and another partially through-wall crack on the other side, both ID-initiated.

Also, cracks at the toe of both the run and branch girth welds were OD-initiated.  Multiple tees on two other units suffered similar creep-related damage.

The material specified was Grade 91. Units were built “to Code,” but analysis found that the materials did not match the plant’s RFQ specifications, although they “came from a reputable OEM.”

Other materials discrepancies were found at the plant.

This is just one example of multiple tee failures in multiple units in the US, and “EPRI has estimated the number of tees potentially at risk could be in the thousands,” Henry said.

Historical perspective 

Years ago, the US electric power industry was seen as a vital component of the economy. “To that end, the industry was regulated to control the risk to which utilities could be exposed and to provide a level of financial security that would encourage investment in the resources (people, equipment, etc) necessary to ensure an ample supply of power,” explained Henry.

This arrangement, he said, “benefited not only the utilities but also the companies that supplied the major plant components—including the steam generators and the turbine/generator equipment.”

OEMs became comprehensive service organizations capable of addressing all aspects including design, manufacturing, erection, commissioning, operations, and materials expertise. OEMs also provided detailed supplier oversight, and direct participation to ensure quality.

“With deregulation, the OEMs’ service capabilities were gradually dismantled,” he said.

Henry then reviewed the ASME Boiler & Pressure Vessel Code, stating that “from the beginning, the focus was on safety. Code was not intended as a design handbook or manual for best manufacturing practices. Design and manufacturing for efficiency and reliability were the OEM’s responsibility,” he explained. The OEMs also provided extensive support to, and participation on, the Code technical committees.

Henry further explained that the ASME Code is for new materials (that is, construction). Repair is in accordance with the National Board Inspection Code (NBIC) and the National Board of Boiler & Pressure Vessel Inspectors.

Today, plant operators are looking for assistance and are often left to choose from a “small pool of technical resources with more narrowly focused capabilities,” particularly regarding materials, welding, and welding engineering. University programs, he further suggested, are also becoming more specialized.

“Plant operators themselves are already stretched to the breaking point,” he added.

Pressure-part materials

Henry turned to a comprehensive overview of some of the more important metallurgy issues encountered in today’s powerplants. He focused on:

  • Principles of ferrous metallurgy.
  • Pressure-part life and creep (Fig 7).
  • Creep damage in welds.

He entitled his presentation Pressure part materials—the basics, but it was quite detailed and comprehensive in the areas of ferrous metallurgy (crystal structures, etc), martensite/pearlite/bainite, microstructures and properties, defects (“all materials contain defects”), hardenability, alloying of steels, common pressure part materials (carbon/low-alloy/CSEF and austenitic stainless steels plus “unwanted but tolerated residual elements in the ore that came along for the ride,” pressure part life and creep, and the structure of welds.

This was all what he called “an overview of some of the more important materials issues faced by plants today.”

Kevin Hayes followed with a discussion on welding and welding engineering support, specifically What industry-wide loss of expertise means for plant owners and operators.

“There is currently a shortage of welders in the US, and the potential shortfall of welders needed by 2027 will be 360,000, according to workforce data provided by the American Welding Society. Potential negative effects of a reduced labor pool include the following:

  • Increased potential for weld-related defects.
  • Competition by employers for limited resources.
  • Use of automation, resulting in less hands-on skilled welders.
  • Potential impacts on outage schedules.

He offered an interesting sidebar caution: “Temporary repairs tend to become permanent.”

Hayes also had several suggestions on the path forward, stating that one competitive advantage will be to have multi-skilled team members (print reading, multiple welding and heat treatment processes, weld machine programming, multiple weld repair processes, etc).

“With the welding and welding engineering support shortage,” he said, “tomorrow’s team members will not be the same as the previous generation’s team members.”

Hayes then turned to detailed looks at potential welding defects, and the best methodology for executing an effective weld repair, including but not limited to:

  • Understand the root cause of the damage or failure and base-material composition.
  • “Sample, sample, sample”—boat samples, in-situ replication, visual and other testing.
  • Evaluate previous repairs.
  • Consider original design, fabrication, and current operating conditions.
  • Define the proper repair method, work scope, and resources required. Creep-related damage, for example, may require full excavation of damage (Fig 8).
  • Execute the plan, then document what was performed and lessons learned.

Another key point: “Be prepared to expand the repair scope to address unexpected conditions.” And most important: “Verify personnel have received proper safety training.”

He then reviewed “NBIC Repair and Alterations, Part 3, Welding Method 6 and Supplement 8 Requirements.”

Pressure-part replacements

Amy Sieben followed with HRSG pressure-part replacements. Citing the age of many units today, she addressed the increasing need for component replacements.

Sieben listed the following as the primary common mechanisms for pressure-part failures:

  • Flow-accelerated corrosion.
  • Under-deposit corrosion.
  • Fatigue cracking.
  • Corrosion fatigue/chemical attack.
  • Creep/fatigue interaction.
  • Dew point corrosion.

This led to discussions on replacements versus chemical cleaning, and the opportunities for material upgrades.

Case studies offered interesting looks at access, trolley systems and lifting/turning frames (Fig 9). Many examples are shared in the presentation.

Other case studies were given on tube and header replacements, NDE and post-weld heat treatment, tube plugging and repair methods, types of tube-to-header welds and weld preparation, and tube restraints.

Sieben then reviewed “the other 10% of failures”—such as baffle/casing systems, desuperheaters and drains, duct liner and expansion joint failures, GT exhaust frames, blowdown piping, etc.

She ended with advanced NDE detection methods, removal and inspection, thermal imaging, radiography, and use of drones.

Don’t forget the stack in your annual inspections

By Team-CCJ | March 12, 2024 | 0 Comments

There are several reasons stacks don’t get much attention from operators on their rounds—among them:

  • They’re static and there’s nothing much to see externally except perhaps peeling paint.
  • Forgetting the switchyard, they’re likely a longer walk from the control room base than any other plant component.
  • Internal access is not possible with the plant in operation.

This means you don’t know much about the true condition of your stack unless you make it a priority to conduct an internal and up-close external inspection annually. Regular inspections can identify problems before they cause an outage, a loss in performance, potential safety issue, etc.

SVI Dynamics’ Scott Shreeg identified several common failure points for a steel stack to be aware of when conducting your annual inspection (photos). They are:

  • General corrosion.
  • Stress or fatigue cracks caused by repetitive or excessive movement. These usually develop at openings or discontinuities in the metal.
  • Buckling of the stack shell caused by corrosion thinning of the shell material.
  • Cracking of the stack shell and its support structure from fatigue attributed to thermal cycling.

Annual inspection checklist

When perusing the list below keep in mind that the inspection and maintenance programs for unlined stacks (single wall) and stacks with a floating liner differ in some respects.

  • Check bolts and nuts for degradation—including anchor bolts, those restraining platforms and ladders, etc.
  • Examine the following for general condition, plus any evidence of corrosion and cracks in base metal and welds:
      • Baseplate.
      • Anchor chairs.
      • Breech opening reinforcement.
      • Shell plate.
      • Circumference stiffeners.
      • Shop and field joints (welded and bolted).
      • Lateral supports.
      • Access doors.
      • Dynamic stability devices.
      • Exterior conditions of test ports.
      • Exterior lagging.
      • Expansion joints.
      • Grounding lugs and cables.
      • Guy wires (visual check for degradation and broken wire strands), cable clamps, and anchors.
      • Platforms and ladders: gratings, handrails, and platform supports.
      • Outer shell-plate coating.
      • Concrete foundation. If cracks are large, a follow-up concrete NDE may be necessary.
  • Thermal imaging is recommended when the inspection must be performed with the unit in service. It is particularly helpful for detecting areas where excessive heat transfer exists because of liner or lagging insulation loss.

Triennial steel-stack inspection

  • Visual inspection of shell plate for the full height of the stack.
  • Random ultrasonic (UT) shell-plate thickness measurements every 10 ft from the bottom of the stack to the top.
  • Follow-up with penetrant or UT inspections of questionable welds.
  • Full-height interior visual inspection, including expansion joints.
  • Drainage condition.
  • Condition of silencers and their supports.
  • Condition of turning vanes, flow dampers, and stack rain cap.
  • Visual inspection for internal floating liner sheets, studs, insulation, batten channels.

When your stack needs go beyond simple inspection

SVI Dynamics has more than 25 years of experience in steel stack design, fabrication, construction, and inspection. This means the company can be a valuable partner for your plant, given its ability to determine the root cause of stack issues uncovered during an inspection and to suggest solutions using today’s most advanced engineering analysis software.

The company’s inspections are conducted to the widely accepted ASCE stack inspection code, with enhancements based on SVI’s experience. Inspections are supervised and reviewed by a registered professional engineer with details provided to the plant.

Inspection reports include the details of stack measurements taken, a summary of root-cause investigations conducted in response to defects found (if any), engineering calculations as needed to support decisions regarding stack structural integrity, and recommendations for follow-up inspection, repairs, and replacements.

Scroll to Top