7FUG 2020: Polling and User Feedback – Combined Cycle Journal

7FUG 2020: Polling and User Feedback

A valuable feature of Power Users conferences is audience polling, which was pioneered by the 7F Users Group a few years ago. The steering committee and presenters use polling to ask owner/operators for their opinions on industry trends, the information needs of attendees, etc. Because the feedback is virtually instantaneous, it can identify where clarification or more detail is required on a particular subject during the presentation of interest.

Below are some of the polling questions asked during the 7F 2020 Digital Conference. The responses both characterize the audience and provide a snapshot of what your industry colleagues are thinking on topics of importance to owner/operators. Users can access presentations from the conference, a plethora of recorded technical presentations, and ask questions on the forum at the Power Users website.

Audience

How many times have you attended a 7F Users Group conference (including this year)?

My first meeting, 46%
Two years, 20%
Three to five years, 21%
Six or more years, 13%

How would you rate your level of 7F knowledge?

Newbie, 14%
Rookie, 10%
Intermediate, 37%
Seasoned, 25%
Expert, 4%

What is your primary role?

Maintenance manager, 12%
Plant manager, 10%
Maintenance engineer, 16%
Turbine engineer, 28%
Asset manager, 11%
Other, 22%

How often do you interact with power traders or dispatchers?

Multiple times a day, 7%
Daily, 22%
Weekly, 12%
Rarely, 29%
Never, 29%

General

What is the average age of your 7F and steam-turbine units based on COD?

Less than 10 years, 15%
10-15 years, 24%
16-20 years, 48%
More than 20 years, 13%

Operations

What system/component gives you the biggest headache, or impacts reliability the most, on your unit(s)? Check all that apply.

  Valves (for example, gas, compressor bleed valves, etc), 45%
Instrumentation (for example, transmitters, T/Cs, etc), 38%
Protection systems (for example, haz-gas detection, etc), 14%
Inlet filtration system, 4%
Covid-19, 12%
Starting system (for example, static starter, etc), 7%

Three years into the future, how do you see your CCGT operating profile changing?

More starts, fewer hours, 50%
More starts, more hours, 13%
Fewer starts, fewer hours, 5%
Fewer starts, more hours, 16%
No change, 15%

Three years into the future, how do you see your CCGT operating and ramp profiles changing?

More part-load operation, more ramping, 65%
More full-load operation, less ramping, 6%
More full-load operation, more ramping, 9%
More part-load operation, less ramping, 3%
No change, 16%

Which type of flexibility would you choose if you could upgrade your plant today?

Higher maximum output, 17%
Lower minimum output, 31%
Faster ramping, 5%
Faster startup, 12%
All of the above, 35%

Plant managers, maintenance managers/engineers, turbine engineers: If you had the ability to cost-effectively cycle overnight versus turndown, would you want to cycle?

Yes, 29%
Absolutely not, 49%
Maybe, 22%

Traders, asset managers: If you had the ability to cost-effectively cycle overnight versus turndown, would you want to cycle?

Yes, 41%
Absolutely not, 37%
Maybe, 22%

Which type of generating unit do you think the more flexible CCGT displaced to produce additional megawatt-hours?

Less-flexible CCGTs, 21%
Simple-cycle GTs, 36%
Steam turbines, 17%
All of the above, 26%

How would you react if your trader/dispatcher asked you to cycle between 2 and 4 a.m.?

No way, 26%
Are you crazy? 21%
OK, as long as power payments make up for the increased maintenance cost, 54%

What was the cause of your last failed start (pick one only)?

Valves, 23%
Static frequency converter, 3%
Burners and nozzles, 7%
Controls, 22%
Instrumentation, 20%
Hardware, 8%
Excitation and generator, 14%
Other, 4%

What concerns you the most at your site for forced-outage days (pick one only)?

Transformer, 19%
Instrumentation, 29%
Rotor, 15%
Bearings, 7%
Steam-turbine unavailable, 19%
Other, 11%

What is your most recent annual unit/block start/stop count on average?

Fewer than 100 start/stops per year, 67%
100-200 start/stops per year, 33%
More than 200 start/stops per year, 0%

In the last 10 years, what start/stop count trend are you experiencing?

Minimal or no change, 56%
Up to 50% increase, 29%
Roughly doubled, 11%
More than doubled, 3%

Which 7F HGP TIL most keeps you up at night?

  2045, 7F AGP Stage 3 bucket tip shroud creep, 40%
2181, Stage 1 nozzle creep degradation model, 23%
2006, 7F and 9F Stage 3 bucket airfoil distress, 17%
Other/none, 20%

Maintenance

What rodent issue have you seen the most?

Cable damage in cable tray, 27%
Wire damage in electrical cabinets, 38%
Insulation damage on piping, 15%
Other, 20%

Do you currently use adjustable rigging in your lift planning for turbine rotor or case removal?

Yes, 66%
No, 34%

Combustion

How familiar are you with gas-turbine combustion?

  I’m a flame-stability expert, 5%
I’m pretty good with what runs in my units, 42%
I know the difference between a DLN 2.6+ and DLN 2.6, 27%
Harry Potter’s wand must be involved, 20%
Gas turbines have combustors? 7%

What is your biggest concern when it comes to combustion operability?

Tuning, 24%
Hardware, 22%
CDM and T/C health, 17%
AutoTune, 15%
Cold weather, 17%
Nothing, my unit runs well, 6%

Have you experienced fuel-nozzle damage?

Yes, 56%
No, 44%

What was the cause of the fuel-nozzle damage?

Quat operation, 8%
Fuel contamination, 28%
Other, 45%
Unknown, 19%

If it was quat operation or unknown, are you changing your quat limits seasonally?

Yes, 13%
No, 86%

Do you have issues during cold weather with high-dynamics alarms that require operator response?

No, 45%
Rarely, 41%
Frequently, 14%

Generators

What is your most common unplanned stator repair/upgrade finding during an outage?

Endwinding dusting/greasing or resonance repair, 69%
Belly-band tightening (or new belly-band install), 8%
Stator rewedge, either full or partial, 23%
Stator core looseness, 0%

What is your most common unplanned field /rotor repair/upgrade finding during an outage?

Slot content (amortisseur spring) migration, 35%
Main lead cracking or separation, 8%
Field turn shorts, 49%
Field ground, 8%

Does your site or HQ/fleet have a spare/exchange 7FH2 field?

Yes, 21%
No, 79%

How much time is on the outage schedule for generator rotor removal and replacement—including setup and tear down?

Less than one day, 7%
Two days, 28%
Almost one week, 48%
Too long, 17%

Auxiliaries

Have you converted to electric actuators on your gas control valves?

Yes, 13%
No, 87%

Are you planning to convert the hydraulic actuators on your gas control valves to electric?

Yes, 11%
No, 57%
Don’t know, 32%

Rotors

How well do you know RLE (rotor lifetime extension)?

  Extremely well. We currently are in discussions and formulating a plan, 35%
Have discussed it with our engine representative, 24%
Know what the acronym stands for, 35%
Don’t know about RLE, 7%

What’s your rotor maintenance plan?

Exchange rotor, 29%
Lifetime extension, 32%
New rotor, 12%
Not decided/do not know, 27%

Is your rotor affected by TILs 1971 and/or 1972?

Yes, 46%
No, 20%
Not sure, 31%
It was, 3%

Is your turbine rotor maintenance hours- or starts-based?

Hours, 52%
Starts, 16%
Multiple units, some with both 27%
Was hours, now starts, 4%
Was starts, now hours, 1%

Do you have maintenance factoring calculated in your DCS logic?

Yes, 14%
No, 37%
Not sure, 16%
Tracking outside the DCS, 33%

Are you planning on conducting 7F rotor maintenance in the next five years?

Yes, based on GER-3620 guidance, 57%
No, 29%
Learning more before deciding, 14%

Exhaust system

How often do you inspect your exhaust-frame flex seals?

HGP interval only, 47%
Annually, 50%
More frequently than annually, 3%

Lubrication

How long does your oil last?

Five years or less, 10%
Six to nine years, 31%
More than nine years, 60%

How many hours do you lose annually because of an oil-related failure?

  Less than 12, 81%
12 to 24, 5%
24 to 48, 9%
More than 48, 5%

What are your MPC values?

Less than 15, 77%
15 to 35, 20%
More than 35, 3%

Does your lab report the MPC hold time as required?

Yes, 13%
No, 28%
Not sure, 59%

What type of lube oil do you use?

Mineral groups 1 and/or 2, 58%
Synthetic hydrocarbon groups 3 and/or 4, 26%
PAG, 16%

Have you used an aftermarket turbine-oil additive?

Yes, 31%
No, 69%

Do you use a varnish-removal system?

No, 30%
Yes, rotating on several units, 33%
Yes, full time, 37%

When did you install your varnish-removal system?

Following a failed lab result, 60%
Following an onsite failure, 28%
With a new charge of oil, 12%

Have you changed the type of lube oil in your gas turbine?

Yes, 29%
Considering it, 20%
No, 51%

What type of evaluation was done prior to changing the type of oil?

Full technical evaluation, 60%
Lube-oil supplier performed the evaluation, 18%
Relied on the experience of others, 22%

perihoki perihoki perihoki perihoki perihoki duta76 duta76 duta76 duta76 duta76 All in mahjong jalan menuju keuntungan Bermain tenang untuk jackpot berlapis Cara menjaga ritme menang terus Pak satria taklukan hambatan hidup lewat mahjong Pola mahjong bukan sekedar tebakan All in dengan hati matang menuju scatter hitam Dari nol ke maxwin dalam tujuh putaran Mahjong all in jadi titik balik finansial Mahjong membuka karier programmer Menggandakan peluang lewat spin bertingkat Modal bisnis dari spin mahjong Putaran mahjong berujung pada scatter beruntun Rasa lega saat all in membuka jalan scatter Dari scatter hitam ke hadiah besar Mahjong sumber kedua penghasilan dokter ternama Peluang emas yang jarang terulang mahjong ways Pemain pilih mahjong saat malam Pola spin gila memaksa hasil mengucur tanpa henti Scatter hitam membuka jalan cepat pemula meraih kemenangan Scatter hitam senjata rahasia mahjong ways Spin dewa memaksa scatter hitam turun Saat pikiran tenang all in jadi langkah besar Spin cepat jarang bantu strategi panjang Spin mastery mengubah putaran jadi peluang Spin murah tak lagi disepelekan setelah buka kunci scatter hitam Teknik profesional menang semua sesi Spin berlapis menarik scatter hitam Spin santai mengundang scatter hitam Spin penuh aksi memperlihatkan scatter hitam terus mengalir Teknik medapatkan hasil besar dari spin pertama